Difference between revisions of "Spring 2019 DIRC Commissioning"
From GlueXWiki
(→Commissioning Observables) |
(→Commissioning Tasks and Milestones) |
||
Line 15: | Line 15: | ||
== Commissioning Tasks and Milestones == | == Commissioning Tasks and Milestones == | ||
− | * | + | * Calibration document with expected tables for CCDB (Oct 22) --- Justin |
− | * Develop scripts for LED timing offset calibration | + | * Develop scripts for LED timing offset calibration (Nov 1) --- Yunjie |
− | * | + | * Develop EVIO parser and Translation Table (Nov 1) --- Bill/Justin |
+ | * | ||
== Commissioning Timeline == | == Commissioning Timeline == |
Revision as of 12:17, 24 September 2018
Contents
Commissioning Goals
- Integrate DIRC readout with general Hall D DAQ and online/offline monitoring
- Confirm cabling through HV/mask checks with LED system
- Calibrate per-pixel timing offset of MAPMTs using LED system
- Determine geometric alignment parameters (position and angle offsets) for optical components
- Implement reconstruction algorithm and compare data/MC: # detected photons, Cherenkov angle resolution
Commissioning Observables
- "Ring" images for tracks with fixed kinematics (binned in position space over bars) overlaid on MC distributions
- Per-pixel timing and Cherenkov angle differences (measured - LUT expected) to confirm geometry
- Number of detected photons/track
- Single photon resolution (SPR) per pixel
Commissioning Tasks and Milestones
- Calibration document with expected tables for CCDB (Oct 22) --- Justin
- Develop scripts for LED timing offset calibration (Nov 1) --- Yunjie
- Develop EVIO parser and Translation Table (Nov 1) --- Bill/Justin
Commissioning Timeline
- July 16-30: Integration of DIRC crate with DAQ and initial test of readout with standalone MAPMT module (Ben, Sergey, Sasha)
- August-October
- Implementation of DAQ decoder for SSP data format in sim-recon to create low level hit objects (David)
- Implementation of Translation Table in CCDB to orient (FPGA, channel ID) mapping from readout into physical pixel coordinates (X, Y) position along readout window (David, Justin, Bill)
- Online and offline monitoring plugins to monitor occupancies and timing distributions (TBD)
- LED occupancy and timing calibration (Yunjie)
- Physics trigger occupancies and timing - possibly use TOF/FCAL as filter for tracks in different regions (TBD)
- Include DIRC hit patterns in event display?
- October 29 - November 18 (3-week install period):
- Verify cabling and translation table with LED data (unique patterns of HV on/off)
- Initial time offset calibrations with LED data
- HV and threshold scans with LED data
- November 19 - December 19 (commissioning with beam):
- TBD
Datasets to acquire with integrated DAQ
HV and threshold scans
- Similar set of HV, MAROC gain, and threshold settings as laser setup for comparison with final implementation
- Validate MAPMT characterization with both LED calibration and beam data
Intensity scans
- Evaluate rate dependence and backgrounds for both high and low luminosity
- Scans of fixed amorphous radiator and varied current from 50 - 300 nA