− | + | * Checking crystals | |
− | + | ::: -Visual inspection: 5 min per crystal | |
− | + | ::: -Dimension measurement: 10 min per crystal | |
+ | ::: -Transmission check: 20 min per crystal (Optional) | ||
+ | ::: -Measure light yield using radioactive source: 20 min per crystal (Optional) | ||
+ | ::: -Measure light yield using PS setup: 12 modules in the PS setup. | ||
− | + | * PMT checking | |
+ | ::: -Diameter check | ||
+ | * Check PMT divider | ||
+ | ::: -Time: 15 min per divider (10 weeks to check 1600 dividers) | ||
+ | ::: -University of Regina, GWU, UNCW | ||
− | * | + | * Preparation of silicon cookie |
+ | :: - Mix RTV625, remove bubbles | ||
+ | :: - Pour to the gluing fixture (prepare 36 cookies can order one more fixture) | ||
+ | :: - Set time: 1 day, full cure time: 4 - 5 days | ||
+ | :: - Time: 3 - 4 hours to load the fixture | ||
− | + | * Check fabricated modules using cosmic ray setup (TBD) | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | * | + | |
− | + | ||
− | + | ||
Line 23: | Line 27: | ||
* Brazing straps | * Brazing straps | ||
− | ::: Time per module | + | ::: Time per module: 20 min |
* ESR shaping | * ESR shaping | ||
:: - ESR cutting | :: - ESR cutting | ||
− | :: - Shape in the oven (2 tools exist, | + | :: - Shape in the oven (2 tools exist, 20 min per cycle] |
− | :: - Time per module | + | :: - Time per module: 20 min |
+ | |||
+ | * Glue light guide to the PMT using UV glue | ||
+ | :: - Time per module: 10 min | ||
* Crystal wrapping | * Crystal wrapping | ||
:: - Cut ESR and Tedlar | :: - Cut ESR and Tedlar | ||
:: - Wrap module | :: - Wrap module | ||
− | :: - Time per module | + | :: - Time per module: 20 min |
* Module fabrication | * Module fabrication | ||
Line 42: | Line 49: | ||
− | ''Total fabrication time: 1 | + | :: '''Total fabrication time: 1 hour 40 min per module''' |
− | + | :::::::: (~5 modules a day, 100 modules a month) | |
− | + | ||
− | :: | + | |
− | :: | + | |
− | :: | + | |
− | + |
Latest revision as of 13:26, 22 April 2021
- Checking crystals
- -Visual inspection: 5 min per crystal
- -Dimension measurement: 10 min per crystal
- -Transmission check: 20 min per crystal (Optional)
- -Measure light yield using radioactive source: 20 min per crystal (Optional)
- -Measure light yield using PS setup: 12 modules in the PS setup.
- PMT checking
- -Diameter check
- Check PMT divider
- -Time: 15 min per divider (10 weeks to check 1600 dividers)
- -University of Regina, GWU, UNCW
- Preparation of silicon cookie
- - Mix RTV625, remove bubbles
- - Pour to the gluing fixture (prepare 36 cookies can order one more fixture)
- - Set time: 1 day, full cure time: 4 - 5 days
- - Time: 3 - 4 hours to load the fixture
- Check fabricated modules using cosmic ray setup (TBD)
Module Fabrication
- Brazing straps
- Time per module: 20 min
- ESR shaping
- - ESR cutting
- - Shape in the oven (2 tools exist, 20 min per cycle]
- - Time per module: 20 min
- Glue light guide to the PMT using UV glue
- - Time per module: 10 min
- Crystal wrapping
- - Cut ESR and Tedlar
- - Wrap module
- - Time per module: 20 min
- Module fabrication
- - Insert mu-metal shield
- - Attach PMT housing, set tension screws
- - Insert PMT with silicon cookies, set tension plate
- - Time per module: 30 min
- Total fabrication time: 1 hour 40 min per module
- (~5 modules a day, 100 modules a month)
- Total fabrication time: 1 hour 40 min per module