Difference between revisions of "August 26, 2021 CPP Design Meeting"
From GlueXWiki
(→Agenda) |
(→Meeting Time and Place) |
||
(9 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
Bluejeans https://bluejeans.com/465620466 | Bluejeans https://bluejeans.com/465620466 | ||
− | * Present - Elton, Dave, Stephanie, Ilya | + | * Present - Elton, Dave, Stephanie, Ilya, Mark S, Simon, Mark I |
== Agenda == | == Agenda == | ||
Line 10: | Line 10: | ||
* Design/Fab/Procurement status | * Design/Fab/Procurement status | ||
** Installation/assy 3D Model and dwgs | ** Installation/assy 3D Model and dwgs | ||
− | ** Stand | + | ** Stand [[image:cpp_stand.pdf|thumb]] |
− | ** Steel | + | ** Steel [[image:cpp_steel.pdf|thumb]] |
** Fcal platform mods | ** Fcal platform mods | ||
− | *** Cutouts complete [[ | + | *** Cutouts complete [[image:cpp_cutout.pdf|thumb]] |
*** Most holes drilled in floor | *** Most holes drilled in floor | ||
* Things to work out | * Things to work out | ||
Line 27: | Line 27: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
+ | * Went over minutes from last meeting | ||
+ | * Looked at 3D model and gave update on procurements | ||
+ | * Discussed testing in EEL - Beni not here - Elton said data is being looked at | ||
+ | * Gas is running low in EEL | ||
+ | |||
+ | ==Action Items == | ||
+ | |||
+ | * Bring more gas bottles to EEL 126 - Mark | ||
+ | * Continue on 3D model and Procurements - Stephanie/Tim |
Latest revision as of 07:08, 9 September 2021
Meeting Time and Place
Thursday August 26, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Mark S, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/July_15,_2021_CPP_Design_Meeting
- Testing status - Beni
- Design/Fab/Procurement status
- Installation/assy 3D Model and dwgs
- Stand
- Steel
- Fcal platform mods
- Cutouts complete
- Most holes drilled in floor
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis - approved by Tom Renzo - need to release into system
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
- CPP Detector operations in Hall D OSP
- Possible use of nitrogen flow for cooling electronics in Faraday cage
Minutes and Action Items
- Went over minutes from last meeting
- Looked at 3D model and gave update on procurements
- Discussed testing in EEL - Beni not here - Elton said data is being looked at
- Gas is running low in EEL
Action Items
- Bring more gas bottles to EEL 126 - Mark
- Continue on 3D model and Procurements - Stephanie/Tim