Difference between revisions of "Hall-B Schedule"
From GlueXWiki
(9 intermediate revisions by 6 users not shown) | |||
Line 2: | Line 2: | ||
− | |||
* ''Earliest occupancy:'' August 16, targeted occupancy: August 22. | * ''Earliest occupancy:'' August 16, targeted occupancy: August 22. | ||
− | * '' | + | * ''[[Installation_Procedures]]:'' craning (1 day), bolting (1 day), survey (1 day), PMT mounting (1 day), cosmics (1-2 weeks) |
− | + | * ''Tentative dates for IU BCAL Cart Shipment:'' Ship Aug. 17-18 for arrival on Aug. 21 | |
+ | * ''Tentative dates for Regina Module Shipment:'' Ship Aug. 13-14 for arrival on Aug. 21 | ||
+ | * ''Tentative dates for Regina personnel:'' Rafael (Aug. 19 - Oct. 3), Blake (Aug 19. - Oct. 3), Kathryn (Aug. 19 - Aug. 26), Zisis (Aug. 19 - Aug. 26, Sep. 19 - Sep. 30), Ioanna (Sep. 19 - Sep. 30), George (Sep. 22 - Sep. 29), Garth (Sep. 22 - Sep. 29), Christine (Sep. 20 - Sep. 27) | ||
+ | * ''Tentative dates for IU personnel:'' Eric (Aug. 20 - Aug.27) | ||
+ | * ''Tentative dates for CUA personel:'' Dan Sober (Sep. 13-14, Sep. 20-Oct. 1), Franz Klein (?), Joe Santoro (?) | ||
+ | * ''Tentative dates for OU personnel:'' Simon Taylor (Sep.5-Oct. 1) | ||
+ | * ''Tentative dates for JLab personnel:'' Daniel S. Carman (Aug. 21 - Oct. 1) | ||
'''The Table below shows the GlueX-related items from the most recent Hall-B schedule.''' | '''The Table below shows the GlueX-related items from the most recent Hall-B schedule.''' |
Latest revision as of 21:11, 23 August 2006
All travel, shipping and task schedule information, in connection to the BCAL beam tests at Hall-B (Sep. 2006), is kept on this page.
- Earliest occupancy: August 16, targeted occupancy: August 22.
- Installation_Procedures: craning (1 day), bolting (1 day), survey (1 day), PMT mounting (1 day), cosmics (1-2 weeks)
- Tentative dates for IU BCAL Cart Shipment: Ship Aug. 17-18 for arrival on Aug. 21
- Tentative dates for Regina Module Shipment: Ship Aug. 13-14 for arrival on Aug. 21
- Tentative dates for Regina personnel: Rafael (Aug. 19 - Oct. 3), Blake (Aug 19. - Oct. 3), Kathryn (Aug. 19 - Aug. 26), Zisis (Aug. 19 - Aug. 26, Sep. 19 - Sep. 30), Ioanna (Sep. 19 - Sep. 30), George (Sep. 22 - Sep. 29), Garth (Sep. 22 - Sep. 29), Christine (Sep. 20 - Sep. 27)
- Tentative dates for IU personnel: Eric (Aug. 20 - Aug.27)
- Tentative dates for CUA personel: Dan Sober (Sep. 13-14, Sep. 20-Oct. 1), Franz Klein (?), Joe Santoro (?)
- Tentative dates for OU personnel: Simon Taylor (Sep.5-Oct. 1)
- Tentative dates for JLab personnel: Daniel S. Carman (Aug. 21 - Oct. 1)
The Table below shows the GlueX-related items from the most recent Hall-B schedule.
ID | Task Name | Work | Duration | Start | Finish | % Work Complete |
---|---|---|---|---|---|---|
151 | GlueX calorimeter | 196 hrs | 9.5 days | Thu 8/3/06 | Wed 8/16/06 | 0% |
152 | Install calorimeter stand | 72 hrs | 3 days | Thu 8/3/06 | Mon 8/7/06 | 0% |
3 | Doug | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
4 | Calvin | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
10 | Crane | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
153 | Install Bcal support | 0 hrs | 1 day | Tue 8/8/06 | Tue 8/8/06 | 0% |
154 | Install calorimeter | 120 hrs | 5 days | Wed 8/9/06 | Tue 8/15/06 | 0% |
3 | Doug | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
4 | Calvin | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
10 | Crane | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
155 | Install Down Stream Helium Bag | 4 hrs | 4 hrs | Wed 8/16/06 | Wed 8/16/06 | 0% |
2 | Steve | 4 hrs | Wed 8/16/06 | Wed 8/16/06 | 0% | |
156 | SURVEY | 44 hrs | 15.63 days | Thu 7/27/06 | Thu 8/17/06 | 0% |
157 | Survey Frascati magnets | 8 hrs | 8 hrs | Tue 8/8/06 | Tue 8/8/06 | 0% |
12 | Survey | 8 hrs | Tue 8/8/06 | Tue 8/8/06 | 0% | |
158 | Survey Pair Spectrometer | 8 hrs | 1 day | Wed 8/9/06 | Wed 8/9/06 | 0% |
12 | Survey | 8 hrs | Wed 8/9/06 | Wed 8/9/06 | 0% | |
159 | Survey GlueX calorimeter | 8 hrs | 1 day | Wed 8/16/06 | Thu 8/17/06 | 0% |
12 | Survey | 8 hrs | Wed 8/16/06 | Thu 8/17/06 | 0% | |
160 | Survey Target | 8 hrs | 1 day | Thu 7/27/06 | Fri 7/28/06 | 0% |
12 | Survey | 8 hrs | Thu 7/27/06 | Fri 7/28/06 | 0% |