Difference between revisions of "Coil Test Weekly Meeting 25-Nov-2009"
From GlueXWiki
m |
m |
||
(3 intermediate revisions by the same user not shown) | |||
Line 9: | Line 9: | ||
'''Agenda''' | '''Agenda''' | ||
− | |||
* Solenoid review aftermath - George | * Solenoid review aftermath - George | ||
* FastTrack schedules: George/Chuck's version and Tom's version - George, Tom | * FastTrack schedules: George/Chuck's version and Tom's version - George, Tom | ||
+ | * QWeak area: when can we get in, how will we use it - Tom | ||
+ | * Design interface to cryo can - George | ||
+ | * Pressure relief system design - George | ||
* Ordering cryo can - George | * Ordering cryo can - George | ||
* Ordering platform - George | * Ordering platform - George | ||
* Construction/installation sequence drawings - George, Chuck | * Construction/installation sequence drawings - George, Chuck | ||
* Ordering remaining controls instrumentation and components - Scot, Elliott | * Ordering remaining controls instrumentation and components - Scot, Elliott | ||
+ | ** 1-channel vs 2-channel A-B RS232 controllers - Elliott | ||
+ | ** Negative voltages, 0-20 mA outputs and A-B input modules: do they match? - Scot, Elliott | ||
+ | ** Do we need an additional A-B chassis? - Scot | ||
+ | ** Do we need additional Dataforth chassis? _ Scot | ||
+ | ** Do we have enough relay channels? - Scot | ||
+ | ** Isolated vs non-isolated voltage channels: do we have enough? - Scot | ||
+ | ** Do we need an additional 19" rack? - Scot | ||
+ | ** Do we need additional rack doors, tops, etc? - Scot, Mark S or Tom | ||
+ | ** Dataforth module voltage requirements: do they match? - Scot | ||
+ | * Can two 19" racks be removed from F117 as a unit? - Scot | ||
* P&I, controls drawings, narrative - George, Mark S, Mark W | * P&I, controls drawings, narrative - George, Mark S, Mark W | ||
* Instrumenting controls racks in F117 - Mark S, Scot | * Instrumenting controls racks in F117 - Mark S, Scot | ||
Line 25: | Line 37: | ||
* Coil 4 controls wiring replacement - George | * Coil 4 controls wiring replacement - George | ||
* Shipping rails from IUCF - Tom | * Shipping rails from IUCF - Tom | ||
+ | * Safety reviews - George, Elliott | ||
+ | * 5 G contours - George | ||
+ | * Modifications to power supply dump resistor wiring - Mark S | ||
* Review [[Solenoid Coil Test|"Top To-Do"]] items - Elliott | * Review [[Solenoid Coil Test|"Top To-Do"]] items - Elliott | ||
* Review of recent progress, identify action items - All | * Review of recent progress, identify action items - All |
Latest revision as of 14:55, 24 November 2009
Solenoid Coil Test Weekly Meeting
Location and Time
- Wed 25-Nov-2009 9:45 am ARC 428
Agenda
- Solenoid review aftermath - George
- FastTrack schedules: George/Chuck's version and Tom's version - George, Tom
- QWeak area: when can we get in, how will we use it - Tom
- Design interface to cryo can - George
- Pressure relief system design - George
- Ordering cryo can - George
- Ordering platform - George
- Construction/installation sequence drawings - George, Chuck
- Ordering remaining controls instrumentation and components - Scot, Elliott
- 1-channel vs 2-channel A-B RS232 controllers - Elliott
- Negative voltages, 0-20 mA outputs and A-B input modules: do they match? - Scot, Elliott
- Do we need an additional A-B chassis? - Scot
- Do we need additional Dataforth chassis? _ Scot
- Do we have enough relay channels? - Scot
- Isolated vs non-isolated voltage channels: do we have enough? - Scot
- Do we need an additional 19" rack? - Scot
- Do we need additional rack doors, tops, etc? - Scot, Mark S or Tom
- Dataforth module voltage requirements: do they match? - Scot
- Can two 19" racks be removed from F117 as a unit? - Scot
- P&I, controls drawings, narrative - George, Mark S, Mark W
- Instrumenting controls racks in F117 - Mark S, Scot
- Should we get help from Chris' group - Elliott
- PLC programming and testing - Mark W
- Coil 1 testing and wire replacement - George
- Coil 2 cost/schedule review, etc. - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails from IUCF - Tom
- Safety reviews - George, Elliott
- 5 G contours - George
- Modifications to power supply dump resistor wiring - Mark S
- Review "Top To-Do" items - Elliott
- Review of recent progress, identify action items - All