Difference between revisions of "Coil Test Weekly Meeting 2-Sep-2010"
From GlueXWiki
m |
|||
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | ==Solenoid Coil Test Weekly Meeting=== | + | ===Solenoid Coil Test Weekly Meeting=== |
Line 9: | Line 9: | ||
'''Agenda''' | '''Agenda''' | ||
+ | * DOE review late Sep | ||
+ | ** overall installation schedule for hall | ||
+ | ** overall schedule for test lab | ||
+ | ** single coil test schedule | ||
+ | ** details of what is being tested | ||
* Installation status | * Installation status | ||
− | |||
** two weeks notice to Errol? | ** two weeks notice to Errol? | ||
* Test plan - Josh | * Test plan - Josh |
Latest revision as of 12:01, 1 September 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 2-Sep-2010 9:30am ARC 428
Agenda
- DOE review late Sep
- overall installation schedule for hall
- overall schedule for test lab
- single coil test schedule
- details of what is being tested
- Installation status
- two weeks notice to Errol?
- Test plan - Josh
- tags, HMI, etc.
- Conduct of Operations
- Magnet power supply and interlock commissioning - Cody
- can we turn it on yet?
- do we have strainers yet?
- Controls racks - Scot
- Strain gauge interlock
- anything else?
- PLC programming/testing status - Mark W
- backup PLC programmer - who?
- tutorial?
- UPS status - Mark W, Elliott
- relay card in interlock system
- connection to PLC
- EPICS <--> PLC communications - Wesley
- connection to guard shack
- HMI and EWEB programming - Yi, Elliott, Hovanes
- status
- tutorial?
- Coil repair status - George
- OSP documents and review - Elliott, George