==Solenoid Coil Test Weekly Meeting===
+
===Solenoid Coil Test Weekly Meeting===
  
  
Line 9: Line 9:
 
'''Agenda'''
 
'''Agenda'''
  
 +
* DOE review late Sep
 +
** overall installation schedule for hall
 +
** overall schedule for test lab
 +
** single coil test schedule
 +
** details of what is being tested
 
* Installation status  
 
* Installation status  
** DOE review late Sep
 
 
** two weeks notice to Errol?
 
** two weeks notice to Errol?
 
* Test plan - Josh
 
* Test plan - Josh

Latest revision as of 12:01, 1 September 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 2-Sep-2010 9:30am ARC 428


Agenda

  • DOE review late Sep
    • overall installation schedule for hall
    • overall schedule for test lab
    • single coil test schedule
    • details of what is being tested
  • Installation status
    • two weeks notice to Errol?
  • Test plan - Josh
    • tags, HMI, etc.
    • Conduct of Operations
  • Magnet power supply and interlock commissioning - Cody
    • can we turn it on yet?
    • do we have strainers yet?
  • Controls racks - Scot
    • Strain gauge interlock
    • anything else?
  • PLC programming/testing status - Mark W
    • backup PLC programmer - who?
    • tutorial?
  • UPS status - Mark W, Elliott
    • relay card in interlock system
    • connection to PLC
  • EPICS <--> PLC communications - Wesley
    • connection to guard shack
  • HMI and EWEB programming - Yi, Elliott, Hovanes
    • status
    • tutorial?
  • Coil repair status - George
  • OSP documents and review - Elliott, George