+ | == Wednesday, Oct 24 at 08:45 == | ||
+ | # Last 24h | ||
+ | #* Beam back after RF-Studies,11:30am | ||
+ | #* TAC run 12:30 to 18:30; partial success, limited statistics, bleed through from Hall A | ||
+ | #* Require TAC data analysis to assess quality and statistics level | ||
+ | #* reasonable smooth data taking over night. | ||
+ | # Reports: | ||
+ | #* [https://logbooks.jlab.org/entry/3614211 Monitoring] | ||
+ | #* [https://logbooks.jlab.org/entry/3614203 DAQ Trigger Rates with diamonds] | ||
+ | #* minor DAQ issues usually roctrig2 | ||
+ | # Plans next few days | ||
+ | #* FAC. Dev.: shifts on standby today 8am till tomorrow 16:00 | ||
+ | #* further details of progress in Fac.Dev. by tomorrow noon. | ||
+ | #* HallD will go to Restricted Access tomorrow morning. | ||
+ | #** For any work in the hall contact Mark Stevens | ||
+ | #* Resume physics data taking over the week end | ||
+ | #** Requires good beam tune (harp scans) | ||
+ | # AoB | ||
+ | #* TAILGATE PARTY THIS AFTERNOON! | ||
+ | |||
+ | == Tuesday, Oct 23 at 08:45 == | ||
+ | # Last 24h | ||
+ | #* After Beam Studies got beam back around 15:30; good data taking [https://logbooks.jlab.org/entry/3613538 so freakin good beam !!!] | ||
+ | #* [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Statistics Spreadsheet] | ||
+ | # Issues | ||
+ | #* Beam energy: [https://logbooks.jlab.org/entry/3613677 logbook entry 3613677] | ||
+ | #* Monitoring: [https://logbooks.jlab.org/entry/3613687 logbook entry 3613687] | ||
+ | # Plan Today | ||
+ | #* RF Recovery only 2h | ||
+ | #* TAC run when beam back (HallC Aerogel installation at least 6h; TAC run with foil! Todd and Mike are available nano BPM should still be up and running with valid calibration. | ||
+ | #* Empty target in prep for TAC run. | ||
+ | # Week forecast | ||
+ | #* Facility development (minimal beam energy spread for hallA beam requirements): Wed. 8am to Thu. 3pm, detailed schedule will be available by 2:30pm this afternoon | ||
+ | #* [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week5.jpg Week 5] | ||
+ | #* [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week6.jpg Week 6] | ||
+ | #* [https://halldweb.jlab.org/wiki-private/index.php/2018_Low_energy_measurements Low energy beam running for this Fall 2018]: discussion today at bi-weekly Gluex Meeting! | ||
+ | #AoB | ||
+ | |||
== Monday, Oct 22 at 08:45 == | == Monday, Oct 22 at 08:45 == | ||
# This past week end | # This past week end |
Latest revision as of 08:33, 24 October 2018
Contents
Wednesday, Oct 24 at 08:45
- Last 24h
- Beam back after RF-Studies,11:30am
- TAC run 12:30 to 18:30; partial success, limited statistics, bleed through from Hall A
- Require TAC data analysis to assess quality and statistics level
- reasonable smooth data taking over night.
- Reports:
- Monitoring
- DAQ Trigger Rates with diamonds
- minor DAQ issues usually roctrig2
- Plans next few days
- FAC. Dev.: shifts on standby today 8am till tomorrow 16:00
- further details of progress in Fac.Dev. by tomorrow noon.
- HallD will go to Restricted Access tomorrow morning.
- For any work in the hall contact Mark Stevens
- Resume physics data taking over the week end
- Requires good beam tune (harp scans)
- AoB
- TAILGATE PARTY THIS AFTERNOON!
Tuesday, Oct 23 at 08:45
- Last 24h
- After Beam Studies got beam back around 15:30; good data taking so freakin good beam !!!
- Statistics Spreadsheet
- Issues
- Beam energy: logbook entry 3613677
- Monitoring: logbook entry 3613687
- Plan Today
- RF Recovery only 2h
- TAC run when beam back (HallC Aerogel installation at least 6h; TAC run with foil! Todd and Mike are available nano BPM should still be up and running with valid calibration.
- Empty target in prep for TAC run.
- Week forecast
- Facility development (minimal beam energy spread for hallA beam requirements): Wed. 8am to Thu. 3pm, detailed schedule will be available by 2:30pm this afternoon
- Week 5
- Week 6
- Low energy beam running for this Fall 2018: discussion today at bi-weekly Gluex Meeting!
- AoB
Monday, Oct 22 at 08:45
- This past week end
- quite smooth running: beam over the week end
- Friday beam tune by Todd: elog entry
- Issues over the week end
- DAQ, gluon04, No PS-trigger on display (DAQ-trigger ok!)
- Data Monitoring
- FCAL performance
- beam intensity issues this morning 7am .... Moday morning start of the work day
- Today:
- Safety walk through
- Tagger beam line vacuum
- After noon beam setup for running. (Todd)
- Week beam forecast
- AoB?
Friday, Oct 19 at 08:45
- Notes from the past 24 hours:
- Alignment of JD70-105 47um in 10 hours. THANKS TO HOVANES!
- Amo run taken
- Harp scan taken: same beam conditions as on Wednesday evening
- PARA and PERP at 0/90 with new diamond in the books!
- Beam last 24h
- Report:
- Actions Required:
- TAKE DATA!
- Weekly Beam forecast: CEBAF-WhiteBoard
- HallA machine development (Tue.-Wed) may shift to Mon.-Tue.!
- Run Plan:
- WTFATRC
- NEED RC in 2 weeks!
- ANY other business
Thursday, Oct 18 at 08:45
- Notes from the past 24 hours:
- re-tune the beam focus was very unsuccessful looking at enhancement.
- according to Todd beam is out of spec considerably in halld beam line.
- beam focus most likely over-focusing?
- Actions Required:
- photon beam, coherent peak!
- need good beam AND diamond for the week end!
- Weekly Beam forecast: CEBAF-WhiteBoard
- Beam studies Monday, HallC 4hour access
- RF recovery Tuesday, HallC aerogel installation
- Wednesday 7am(?) to Thursday midnight Hall-A beam tune. No beam or only parasitic other halls.
- take advantage of down for installations?
- TAC postpone to Friday 10/26?????
- Reports:
- photon beam spot still perfectly centered
- Data Monitoring?
- Statistics Spreadsheet
- Run Plan