Difference between revisions of "Run Planning Meeting Notes, Nov 8-Nov 14, 2018"
From GlueXWiki
(→Friday, Nov 9 at 08:45) |
(→Wednesday, Nov 14 at 08:45) |
||
(26 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
* [https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2018-08/index.html Trigger graphs] | * [https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2018-08/index.html Trigger graphs] | ||
* [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Trigger Spreadsheet] | * [https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Trigger Spreadsheet] | ||
+ | *Low energy running [https://docs.google.com/spreadsheets/d/1qJv80NKS1zCrBj5utogCAIBo5KZXtTocV0fc5pqfx_0/edit?usp=sharing Trigger Spreadsheet] | ||
+ | |||
+ | ---- | ||
+ | |||
* [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] | * [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] | ||
* [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Plan Google Calendar] | * [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Plan Google Calendar] | ||
Line 9: | Line 13: | ||
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week8.jpg Hall D schedule for week 8] | *[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week8.jpg Hall D schedule for week 8] | ||
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week9.jpg Hall D schedule for week 9] | *[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week9.jpg Hall D schedule for week 9] | ||
+ | |||
+ | |||
+ | == Wednesday, Nov 14 at 08:45 == | ||
+ | |||
+ | #Last 24h: | ||
+ | #* [https://logbooks.jlab.org/entry/3625626 Installation of beam pipe] | ||
+ | #* Harp scan [https://logbooks.jlab.org/entry/3625678] [https://logbooks.jlab.org/entry/3625679] [https://logbooks.jlab.org/entry/3625682] [https://logbooks.jlab.org/entry/3625708]: [https://logbooks.jlab.org/entry/3625709 Proposal for convergence] | ||
+ | #* Switch back to standard production running: | ||
+ | #** Ramp up PS magnet to 910A (done) | ||
+ | #** Low-energy tagger counters off (done) | ||
+ | #** [https://logbooks.jlab.org/entry/3625826 Set coherent peak at 8.8GeV] (done) | ||
+ | #Issues | ||
+ | #* [https://logbooks.jlab.org/entry/3625720 Reconstructed beam energy plot]: [https://logbooks.jlab.org/entry/3625751 Energy range restored, horizontal scale adapted] | ||
+ | #* [https://logbooks.jlab.org/entry/3625739 FCAL scalers] | ||
+ | #Reports | ||
+ | #* [https://logbooks.jlab.org/entry/3625997 Monitoring] (Thomas) | ||
+ | #* [https://logbooks.jlab.org/entry/3625972 Rates] (Alexandre) | ||
+ | #* [https://logbooks.jlab.org/entry/3625774 ComCal] (Sasha) | ||
+ | #Plans | ||
+ | #* Beam tuning | ||
+ | #* Production running | ||
+ | #* TAC run: Thursday while Sasha is on shift? | ||
+ | #Notes | ||
+ | |||
+ | == Tuesday, Nov 13 at 08:45 == | ||
+ | |||
+ | #Last 24h: | ||
+ | #* 6h+ scheduled down time due to system recovery, but many problems | ||
+ | #* Preparations for beam pipe installation (done) | ||
+ | #* Upgrade to Hall D current locks + beam based test (30min) | ||
+ | #* Only very little beam during the night, accelerator harp scan done [https://logbooks.jlab.org/entry/3625346][https://logbooks.jlab.org/entry/3625351], ours interrupted | ||
+ | #* Switch back to standard production running: | ||
+ | #** Ramp up PS magnet to 910A (done) | ||
+ | #** Low-energy tagger counters off (done) | ||
+ | #** Set coherent peak at 8.8GeV ('''not done''') | ||
+ | #Issues | ||
+ | #* [https://logbooks.jlab.org/entry/3624986 Hot FCAL channel] | ||
+ | #Reports | ||
+ | #* Monitoring (Thomas) | ||
+ | #* [https://logbooks.jlab.org/entry/3625122 Rho polarization for low-energy run] (Alex) | ||
+ | #Plans | ||
+ | #* Beam Studies (Tuesday 08:30, 8h): installation of beam pipe | ||
+ | #* French delegation to visit ComCal (6 people) | ||
+ | #* Harp scan | ||
+ | #* Production running | ||
+ | #Notes | ||
+ | |||
+ | == Monday, Nov 12 at 08:45 == | ||
+ | |||
+ | #Last 72h: | ||
+ | #* 6h down time on Friday due to HV issue on RF cavity 1L23 | ||
+ | #* 12h down on Saturday due to 1L23 and more | ||
+ | #* 4h down on Sunday | ||
+ | #* Completed the goal of 5 full cycles (2B events) on Sunday ~5pm | ||
+ | #Issues | ||
+ | #* [https://logbooks.jlab.org/entry/3624685 Hot FCAL channel] | ||
+ | #Reports | ||
+ | #* [https://logbooks.jlab.org/entry/3624353 Friday morning harp scan] fitted with [https://logbooks.jlab.org/entry/3624320 new online tool (Richard)] | ||
+ | #* [https://logbooks.jlab.org/entry/3623477 Transmission check] | ||
+ | #* [https://logbooks.jlab.org/entry/3624456 Sunday morning harp scan] | ||
+ | #* [https://logbooks.jlab.org/entry/3624871 Monitoring (Thomas)] | ||
+ | #* [https://logbooks.jlab.org/entry/3624862 Rates (Alexandre)] | ||
+ | #Plans | ||
+ | #* System Recovery (Monday 07:30, 6h+): switching back to 8.8GeV running? | ||
+ | #* Beam Studies (Tuesday 08:30, 8h): installation of beam pipe | ||
+ | #Notes | ||
== Friday, Nov 9 at 08:45 == | == Friday, Nov 9 at 08:45 == | ||
#Last 24h: | #Last 24h: | ||
+ | #*>80% beam available, >95% used | ||
+ | #*completed 2nd cycle | ||
+ | #*harp scan ongoing | ||
#Issues | #Issues | ||
− | # Sluggish CSS, investigating | + | #*Sluggish CSS during the day, investigating |
+ | #*[https://logbooks.jlab.org/entry/3623095 Tagger dump BPM AD00c] | ||
#Reports | #Reports | ||
+ | #*[https://logbooks.jlab.org/entry/3623383 Rates] | ||
+ | #*[https://logbooks.jlab.org/entry/3623404 Monitoring report] | ||
+ | #*[https://logbooks.jlab.org/entry/3623250 PS energy range] | ||
#Plans | #Plans | ||
+ | #* Beam Studies and System Recovery switched | ||
+ | #* System Recovery (Monday 08:30): investigate water leak in tunnel, ~3h | ||
+ | #* Beam Studies (Tuesday): high current test, halls A, B and C have to stayed locked, D optional | ||
#Notes | #Notes | ||
Latest revision as of 10:54, 14 November 2018
<- Back to Run Coordination Meetings:Fall2018 Run
- Trigger graphs
- Trigger Spreadsheet
- Low energy running Trigger Spreadsheet
- Run Plan Google Calendar
- Accel. Plan Google Calendar
- Acc whiteboard
- Counting house whiteboard
- Hall D schedule for week 8
- Hall D schedule for week 9
Contents
Wednesday, Nov 14 at 08:45
- Last 24h:
- Installation of beam pipe
- Harp scan [1] [2] [3] [4]: Proposal for convergence
- Switch back to standard production running:
- Ramp up PS magnet to 910A (done)
- Low-energy tagger counters off (done)
- Set coherent peak at 8.8GeV (done)
- Issues
- Reports
- Monitoring (Thomas)
- Rates (Alexandre)
- ComCal (Sasha)
- Plans
- Beam tuning
- Production running
- TAC run: Thursday while Sasha is on shift?
- Notes
Tuesday, Nov 13 at 08:45
- Last 24h:
- 6h+ scheduled down time due to system recovery, but many problems
- Preparations for beam pipe installation (done)
- Upgrade to Hall D current locks + beam based test (30min)
- Only very little beam during the night, accelerator harp scan done [5][6], ours interrupted
- Switch back to standard production running:
- Ramp up PS magnet to 910A (done)
- Low-energy tagger counters off (done)
- Set coherent peak at 8.8GeV (not done)
- Issues
- Reports
- Monitoring (Thomas)
- Rho polarization for low-energy run (Alex)
- Plans
- Beam Studies (Tuesday 08:30, 8h): installation of beam pipe
- French delegation to visit ComCal (6 people)
- Harp scan
- Production running
- Notes
Monday, Nov 12 at 08:45
- Last 72h:
- 6h down time on Friday due to HV issue on RF cavity 1L23
- 12h down on Saturday due to 1L23 and more
- 4h down on Sunday
- Completed the goal of 5 full cycles (2B events) on Sunday ~5pm
- Issues
- Reports
- Plans
- System Recovery (Monday 07:30, 6h+): switching back to 8.8GeV running?
- Beam Studies (Tuesday 08:30, 8h): installation of beam pipe
- Notes
Friday, Nov 9 at 08:45
- Last 24h:
- >80% beam available, >95% used
- completed 2nd cycle
- harp scan ongoing
- Issues
- Sluggish CSS during the day, investigating
- Tagger dump BPM AD00c
- Reports
- Plans
- Beam Studies and System Recovery switched
- System Recovery (Monday 08:30): investigate water leak in tunnel, ~3h
- Beam Studies (Tuesday): high current test, halls A, B and C have to stayed locked, D optional
- Notes
Thursday, Nov 8 at 08:45
- Last 24h:
- TAC run with empty target, v-wire at 50nA, reduced field in PS (400A), low E TAGH counters on
- Harp Scan
- Beam tuning (deferred)
- Data taking with reduced PS field, coherent edge at 7GeV
- TAGH Rates (Amo), (Diamond), Coincidence Rates
- Low energy running Trigger Spreadsheet
- RF problems in the night
- Issues
- PS and PSC coincidence scalers frozen, ps_client running on gluon100 restarted, instructions in hdops wiki
- beam position went awry, rates soared, reference module for IOC reading out 5C11B failed, replaced
- EPICS froze for 2h, started working without intervention, now again unresponsive
- Target PTR turned off, do not ignore any alarms!
- Reports
- Plans
- Notes