Difference between revisions of "Run Planning Meeting Notes, Nov 14-Nov 21, 2018"
From GlueXWiki
m (→Wednesday, Nov 20 at 08:45) |
|||
(26 intermediate revisions by 2 users not shown) | |||
Line 14: | Line 14: | ||
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week9.jpg Hall D schedule for week 9] | *[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week9.jpg Hall D schedule for week 9] | ||
*[https://halldweb.jlab.org/wiki/images/9/90/Fall18_week10.jpg Hall D schedule for week 10] | *[https://halldweb.jlab.org/wiki/images/9/90/Fall18_week10.jpg Hall D schedule for week 10] | ||
+ | |||
+ | |||
+ | |||
+ | == Wednesday, Nov 21 at 08:45 == | ||
+ | |||
+ | #Last 24h: | ||
+ | #* Baseline calibration: Sergei, Beni. | ||
+ | #* Luminosity studies | ||
+ | #* Harp Scan [http://zeus.phys.uconn.edu/halld/cobrems/harptool.cgi?harp5C11_xsigma=1.535&harp5C11_xsigma_err=0.04&harp5C11_ysigma=1.221&harp5C11_ysigma_err=0.04&harp5C11B_xsigma=1.456&harp5C11B_xsigma_err=0.04&harp5C11B_ysigma=0.916&harp5C11B_ysigma_err=0.04&radHarp_xsigma=1.388&radHarp_xsigma_err=0.2&radHarp_ysigma=0.7697&radHarp_ysigma_err=0.2&harp5C11_spos=102.97&harp5C11B_spos=115.11&emittance_x=0.0062&radHarp_spos=119.7&emittance_y=0.0044&collimator_spos=194.92&fit=fit+and+plot] | ||
+ | #Issues | ||
+ | #* [https://logbooks.jlab.org/entry/3629008 tagger magnetic field] Hovanes | ||
+ | #Reports | ||
+ | #* [https://logbooks.jlab.org/entry/3628918 DCs status during luminosity studies] Lubomir, Beni. | ||
+ | #* [https://logbooks.jlab.org/entry/3629292 Rates during luminosity study] (Alexandre D.) | ||
+ | #* [https://logbooks.jlab.org/entry/3629317 Monitoring report] (Thomas) | ||
+ | #Plans | ||
+ | #* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for last week] | ||
+ | #* [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week10.jpg Time chart for this week] | ||
+ | #* Luminosity study. | ||
+ | #* Harp Scan | ||
+ | #Discussion ComCal commissioning | ||
+ | #* [https://halldweb.jlab.org/wiki/index.php/File:Run_Plan_Fall_2018-v3c.jpg Latest runplan (V.3c) ] | ||
+ | #* Time chart, updated after 11/15/2018 discussion | ||
+ | #** [https://halldweb.jlab.org/wiki/images/c/ca/Fall18_week11.jpg Week 11] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/8/8b/Fall18_week12.jpg Week 12] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/5/50/Fall18_week13.jpg Week 13] | ||
+ | #Notes | ||
+ | |||
+ | == Tuesday, Nov 20 at 08:45 == | ||
+ | |||
+ | #Last 24h: | ||
+ | #* [https://logbooks.jlab.org/entry/3628470 FCal HV scan] (A. Somov) | ||
+ | #* 2pm-6pm: optic optimization (T. Satogata) | ||
+ | #* Standard production running | ||
+ | #Issues | ||
+ | #* Optic tuning unsuccessful: [https://logbooks.jlab.org/entry/3628637 background on our Harp scan 100 times larger] and some of the tagger radiation monitors have twice larger signals. Scrapping is likely the cause. MCC backed-out of the new optics. [https://logbooks.jlab.org/entry/3628675 Harp background] and radiation monitor signals back to normal. Transmission back to the same as Monday morning (still 15% lower than at the start of the month). | ||
+ | #* [https://logbooks.jlab.org/entry/3628838 Coherent peak shape] (Beni) | ||
+ | #Reports | ||
+ | #* [https://logbooks.jlab.org/entry/3628831 Monitoring report] (Thomas) | ||
+ | #Plans | ||
+ | #* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week] | ||
+ | #*<font color="red"><b>Luminosity study. [https://docs.google.com/spreadsheets/d/1UT3o4yJ-avlIQzmZKJo2nRrgVPzYKJvGPJ0oqAn81Oo/edit?usp=sharing Plan] </b></font>J. Stevens | ||
+ | #* Standard production running | ||
+ | #Discussion ComCal commissioning | ||
+ | #* [https://halldweb.jlab.org/wiki/index.php/File:Run_Plan_Fall_2018-v3c.jpg Latest runplan (V.3c) ] | ||
+ | #* Time chart, updated after 11/15/2018 discussion | ||
+ | #** [https://halldweb.jlab.org/wiki/images/c/ca/Fall18_week11.jpg Week 11] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/8/8b/Fall18_week12.jpg Week 12] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/5/50/Fall18_week13.jpg Week 13] | ||
+ | #Notes | ||
+ | |||
+ | == Monday, Nov 19 at 08:45 == | ||
+ | |||
+ | #Last 72h: | ||
+ | #* Friday Morning: Optic optimization | ||
+ | #* [https://logbooks.jlab.org/entry/3627249 TAC run] (Alexander S.) | ||
+ | #* Empty target run+ raw mode run | ||
+ | #* Standard production running | ||
+ | #Issues | ||
+ | #* [https://logbooks.jlab.org/entry/3627619 Rate are significantly lower after beam optimization. Diamond orientation dependence] (Alexandre D.). This is due to bad beam profile: The optimization done on Friday by Todd S. did not last: | ||
+ | #**[https://logbooks.jlab.org/entry/3627155 Harp result for Friday after the optimization] | ||
+ | #**Harps result for Saturday [https://logbooks.jlab.org/entry/3627661 1], [https://logbooks.jlab.org/entry/3627915 2] | ||
+ | #**[https://logbooks.jlab.org/entry/3628194 Harps results for Sunday] | ||
+ | #* [https://logbooks.jlab.org/entry/3627399 GONI camera is not communicating] (Hovanes) | ||
+ | #* [https://logbooks.jlab.org/entry/3628105 FCAL pulser] (Elton) | ||
+ | #Reports | ||
+ | #* [http://zeus.phys.uconn.edu/halld/cobrems/harptool.cgi Richard made is tool to compute the beam profile available for general use.] | ||
+ | #* [https://logbooks.jlab.org/entry/3628424 Monitoring report] (Thomas) | ||
+ | #Plans | ||
+ | #* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week] | ||
+ | #* 30 min FCal scan (A. Somov) | ||
+ | #* 2pm: optic optimization (T. Satogata) | ||
+ | #* Standard production running | ||
+ | #Discussion ComCal commissioning | ||
+ | #* [https://halldweb.jlab.org/wiki/index.php/File:Run_Plan_Fall_2018-v3c.jpg Latest runplan (V.3c) ] | ||
+ | #* Time chart, updated after 11/15/2018 discussion | ||
+ | #** [https://halldweb.jlab.org/wiki/images/c/ca/Fall18_week11.jpg Week 11] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/8/8b/Fall18_week12.jpg Week 12] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/5/50/Fall18_week13.jpg Week 13] | ||
+ | #Notes | ||
== Friday, Nov 16 at 08:45 == | == Friday, Nov 16 at 08:45 == | ||
#Last 24h: | #Last 24h: | ||
− | #* Check V-wire rate in preparation for TAC on Friday. ( | + | #* Check V-wire rate in preparation for TAC on Friday. (Alexander S.) |
− | #* Check issue with CBrem gui. It appears to be gone (Hovanes) | + | #* Check issue with CBrem gui. [https://logbooks.jlab.org/entry/3626532 It appears to be gone] (Hovanes) |
#* Maintenance: 1pm-4/5pm. | #* Maintenance: 1pm-4/5pm. | ||
− | #** Access: flux monitor (Tim); FCal (Colin) | + | #** Access: [https://logbooks.jlab.org/entry/3626690 flux monitor] (Tim); FCal (Colin) |
#* Standard production running | #* Standard production running | ||
#Issues | #Issues | ||
− | #* [https://logbooks.jlab.org/entry/3627046 Beam energy monitoring] | + | #* [https://logbooks.jlab.org/entry/3627046 Beam energy monitoring] (Alexandre D.) |
+ | #* [https://logbooks.jlab.org/entry/3626628 Shift checklist rejuvenation] (Elton) | ||
#Reports | #Reports | ||
− | #* [ | + | #* [https://logbooks.jlab.org/entry/3626620 Energy dependent rho polarization for low-energy running] (Alexander A.) |
+ | #* Monitoring report (Thomas) | ||
#Plans | #Plans | ||
#* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week] | #* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week] | ||
Line 32: | Line 114: | ||
#* TAC run this morning/afternoon. | #* TAC run this morning/afternoon. | ||
#* Standard production running over the week end. | #* Standard production running over the week end. | ||
+ | #Discussion ComCal commissioning | ||
+ | #* [https://halldweb.jlab.org/wiki/index.php/File:Run_Plan_Fall_2018-v3c.jpg Latest runplan (V.3c) ] | ||
+ | #* Time chart, updated after 11/15/2018 discussion | ||
+ | #** [https://halldweb.jlab.org/wiki/images/c/ca/Fall18_week11.jpg Week 11] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/8/8b/Fall18_week12.jpg Week 12] | ||
+ | #** [https://halldweb.jlab.org/wiki/images/5/50/Fall18_week13.jpg Week 13] | ||
#Notes | #Notes | ||
+ | #*No meetings this week end. | ||
== Thursday, Nov 15 at 08:45 == | == Thursday, Nov 15 at 08:45 == |
Latest revision as of 05:07, 22 November 2018
<- Back to Run Coordination Meetings:Fall2018 Run
- Trigger graphs
- Trigger Spreadsheet
- Low energy running Trigger Spreadsheet
- Run Plan Google Calendar
- Accel. Plan Google Calendar
- Acc whiteboard
- Counting house whiteboard
- Hall D schedule for week 9
- Hall D schedule for week 10
Contents
Wednesday, Nov 21 at 08:45
- Last 24h:
- Baseline calibration: Sergei, Beni.
- Luminosity studies
- Harp Scan [1]
- Issues
- tagger magnetic field Hovanes
- Reports
- DCs status during luminosity studies Lubomir, Beni.
- Rates during luminosity study (Alexandre D.)
- Monitoring report (Thomas)
- Plans
- Time chart for last week
- Time chart for this week
- Luminosity study.
- Harp Scan
- Discussion ComCal commissioning
- Latest runplan (V.3c)
- Time chart, updated after 11/15/2018 discussion
- Notes
Tuesday, Nov 20 at 08:45
- Last 24h:
- FCal HV scan (A. Somov)
- 2pm-6pm: optic optimization (T. Satogata)
- Standard production running
- Issues
- Optic tuning unsuccessful: background on our Harp scan 100 times larger and some of the tagger radiation monitors have twice larger signals. Scrapping is likely the cause. MCC backed-out of the new optics. Harp background and radiation monitor signals back to normal. Transmission back to the same as Monday morning (still 15% lower than at the start of the month).
- Coherent peak shape (Beni)
- Reports
- Monitoring report (Thomas)
- Plans
- Time chart for this week
- Luminosity study. Plan J. Stevens
- Standard production running
- Discussion ComCal commissioning
- Latest runplan (V.3c)
- Time chart, updated after 11/15/2018 discussion
- Notes
Monday, Nov 19 at 08:45
- Last 72h:
- Friday Morning: Optic optimization
- TAC run (Alexander S.)
- Empty target run+ raw mode run
- Standard production running
- Issues
- Rate are significantly lower after beam optimization. Diamond orientation dependence (Alexandre D.). This is due to bad beam profile: The optimization done on Friday by Todd S. did not last:
- Harp result for Friday after the optimization
- Harps result for Saturday 1, 2
- Harps results for Sunday
- GONI camera is not communicating (Hovanes)
- FCAL pulser (Elton)
- Rate are significantly lower after beam optimization. Diamond orientation dependence (Alexandre D.). This is due to bad beam profile: The optimization done on Friday by Todd S. did not last:
- Reports
- Plans
- Time chart for this week
- 30 min FCal scan (A. Somov)
- 2pm: optic optimization (T. Satogata)
- Standard production running
- Discussion ComCal commissioning
- Latest runplan (V.3c)
- Time chart, updated after 11/15/2018 discussion
- Notes
Friday, Nov 16 at 08:45
- Last 24h:
- Check V-wire rate in preparation for TAC on Friday. (Alexander S.)
- Check issue with CBrem gui. It appears to be gone (Hovanes)
- Maintenance: 1pm-4/5pm.
- Access: flux monitor (Tim); FCal (Colin)
- Standard production running
- Issues
- Beam energy monitoring (Alexandre D.)
- Shift checklist rejuvenation (Elton)
- Reports
- Energy dependent rho polarization for low-energy running (Alexander A.)
- Monitoring report (Thomas)
- Plans
- Time chart for this week
- Optics adjustment (Todd/Jay) 30 min.
- TAC run this morning/afternoon.
- Standard production running over the week end.
- Discussion ComCal commissioning
- Latest runplan (V.3c)
- Time chart, updated after 11/15/2018 discussion
- Notes
- No meetings this week end.
Thursday, Nov 15 at 08:45
- Last 24h:
- Standard production running
- Issues
- CBrem gui not fitting and the coherent edge has been drifting. Decided (6am) to stop run on diamond, do Harp scan and continue with amorphous run, then TAC until the problem is fixed.
- Convergence optimization failed because optics has drifted compared to yesterday, the basis for how to carry the optimization. Rates after optimization did not show improvement.
- Beam current has been unusually unstable yesterday [Some fluctuations of current correlates with beam position drift https://logbooks.jlab.org/entry/3626367]
- Reports
- Monitoring (Thomas)
- Plans
- Monday maintenance is moved to today, 1pm-4/5pm.
- Check V-wire position wrt beam (Sacha).
- Investigate issue with CBrem gui. Meanwhile, fill the target.
- Production running, starting with amorphous (for CBrem ref.)
- Optics adjustment (Todd/Jay) 30 min.
- Access to move back the flux monitor
- Other access?
- TAC run this morning/afternoon is postponed.
- Optics adjustment (Todd/Jay) 30 min.
- Discussion ComCal commissioning
- Notes