Difference between revisions of "Run Planning Meeting Notes, Feb 28 - Mar 6, 2019"
From GlueXWiki
(→Thursday, Feb. 28 at 08:45) |
m (Jonesrt moved page Run Planning Meeting Notes, Feb. 28-Mar 6, 2019 to Run Planning Meeting Notes, Feb 28 - Mar 6, 2019) |
||
(26 intermediate revisions by 2 users not shown) | |||
Line 4: | Line 4: | ||
* [[Run_Coordination_Meetings:Spring2019_Run]] | * [[Run_Coordination_Meetings:Spring2019_Run]] | ||
* [https://halldweb.jlab.org/wiki/index.php/Spring_2019_Primex PrimEx-η run plan] | * [https://halldweb.jlab.org/wiki/index.php/Spring_2019_Primex PrimEx-η run plan] | ||
+ | * [https://halldweb.jlab.org/primexd/prod_spring_2019/run_list.pdf Production runs, number of triggers] | ||
* To join via a Web Browser, go to the page [https://bluejeans.com/660743227 https://bluejeans.com/660743227] | * To join via a Web Browser, go to the page [https://bluejeans.com/660743227 https://bluejeans.com/660743227] | ||
Line 23: | Line 24: | ||
#* LHe target installation: | #* LHe target installation: | ||
#** Hall open at 6 am for bleeding up beamline | #** Hall open at 6 am for bleeding up beamline | ||
− | #** Other work in the Hall: | + | |
+ | |||
+ | == Friday, Mar. 1 at 08:45 == | ||
+ | # Past 24 hours: | ||
+ | #* [https://logbooks.jlab.org/entry/3661211 Be target removed Thursday morning] | ||
+ | #* [https://logbooks.jlab.org/entry/3661206 Examination of material in beamline] | ||
+ | #* [https://logbooks.jlab.org/comment/20469#comment-20469 Shift in CompCal acceptance along +x] | ||
+ | #** FCAL survey from 2015 shows it is shifted in +x direction by 0.53 cm, which matches the shift in CompCal acceptance | ||
+ | # Compton production statistics: [https://halldweb.jlab.org/primexd/prod_spring_2019/run_list.pdf summary run list] | ||
+ | #* 0.24 billion triggers with no target ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61308&runTo=61311&q=beam_current+%3E+25+and+event_count%3E5e5 Runs 61308-61311]) | ||
+ | #* 2.86 billion triggers with Be ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61321&runTo=61344&q=beam_current+%3E+25+and+event_count%3E5e5 Runs 61321-61344]) | ||
+ | #* 0.42 billion triggers with empty target holder cylinder ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61345&runTo=61354&q=beam_current+%3E+25+and+event_count%3E5e5 Runs 61345-61354]) | ||
+ | #* Summary: Empty target is ~25% of statistics for Be target running | ||
+ | # Today's plan: | ||
+ | #* LHe target installation (ongoing): | ||
+ | #** Hall opened at 6 am for bleeding up beamline and target removal | ||
+ | #** Target installation ongoing and S&A to fiducialize and align target around 10 am | ||
+ | #** Other work in the Hall: | ||
+ | #*** Start counter installation status: cabled and signals checked? who? | ||
+ | #*** Others? | ||
+ | #* Empty (evacuated) LHe cell running overnight | ||
# LHe target cooldown and filling schedule? | # LHe target cooldown and filling schedule? | ||
#* Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill. | #* Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill. | ||
#* Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday? | #* Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday? | ||
+ | # Plans for next week: | ||
+ | #* Beam studies on Monday: | ||
+ | #** Parity studies in Hall A from 8:30-12 | ||
+ | #** Todd will work on improving Hall D optics and convergence from 12-4 | ||
+ | #* RF recovery on Tuesday: expected but don't know duration yet | ||
+ | |||
+ | |||
+ | == Monday, Mar. 4 at 08:45 == | ||
+ | # Past 72 hours: | ||
+ | #* [https://logbooks.jlab.org/entry/3661946 LHe target installation] and [https://logbooks.jlab.org/entry/3662109 followup with leak detector] | ||
+ | #* [https://logbooks.jlab.org/entry/3662073 Accelerator vacuum issue] | ||
+ | #* Observations with FCAL channels: [https://logbooks.jlab.org/entry/3662230 Suspicious channel in the inner FCAL ring] and [https://logbooks.jlab.org/entry/3662284 status from Be running] | ||
+ | # Production statistics: [https://halldweb.jlab.org/primexd/prod_spring_2019/run_list.pdf summary run list] | ||
+ | #* 0.86 billion triggers with empty LHe target ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61357&runTo=61375&q=beam_current+%3E+25+and+event_count%3E5e5 61357-61375 (still ongoing)]) | ||
+ | # Data monitoring and analysis: | ||
+ | #* [https://logbooks.jlab.org/entry/3661880 Added CCAL_online plugin to RootSpy] | ||
+ | #* Empty LHe target runs in PlotBrowser: Any issues observed for other detectors? | ||
+ | #* [https://logbooks.jlab.org/entry/3662704 Be target statistics] (Ilya) | ||
+ | #* [https://logbooks.jlab.org/entry/3662254 CCAL and Be surveys] (Sasha) | ||
+ | # Today's plan: | ||
+ | #* LHe target vacuum investigation | ||
+ | #* Other work in the Hall: FCAL? Others? | ||
+ | #* Beam studies complete around noon, back to production if target ready. | ||
+ | # Tomorrow's plan: | ||
+ | #* RF recovery expected but don't know duration yet | ||
+ | #* Access for other work in Hall? Probably depends on what is found Monday with target. | ||
+ | |||
+ | |||
+ | == Tuesday, Mar. 5 at 08:45 == | ||
+ | # Past 24 hours: | ||
+ | #* [https://logbooks.jlab.org/entry/3663156 LHe target vacuum investigation] and [https://logbooks.jlab.org/entry/3663164 filling LHe target] | ||
+ | #* [https://logbooks.jlab.org/entry/3662951 FCAL base replacement] | ||
+ | #* Accelerator has continuing RF issues maintaining gradient for this beam energy, therefore [https://logbooks.jlab.org/entry/3663391 the energy will be lowered to 11.2 GeV for the remainder of the run.] | ||
+ | #** Beam could be delivered to Hall D by Thursday day shift at the earliest, but Thursday swing shift more likely. | ||
+ | #** Propose to cancel shifts through Thursday owl, and put Thursday day on standby. | ||
+ | # Production statistics: [https://halldweb.jlab.org/primexd/prod_spring_2019/run_list.pdf summary run list] | ||
+ | #* 0.89 billion triggers with empty LHe target ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61357&runTo=61375&q=beam_current+%3E+25+and+event_count%3E5e5 61357-61375]) | ||
+ | #* 0.45 billion triggers with filled LHe target ([https://halldweb.jlab.org/rcdb/runs/search?runFrom=61378&runTo=61391&q=beam_current+%3E+25+and+event_count%3E5e5 61378-61391]) | ||
+ | # Issues: | ||
+ | #* Improve camera focus on target cart? | ||
+ | # Data monitoring and analysis: | ||
+ | #* [https://logbooks.jlab.org/entry/3663403 Rate monitoring] (Alexandre) | ||
+ | #* Empty and Full LHe target runs in PlotBrowser: Any issues? | ||
+ | # Today's plan: | ||
+ | #* RF recovery 8:30 am - 3 pm | ||
+ | #* Do we need restricted access for work in the Hall? |
Latest revision as of 07:20, 21 March 2019
Contents
- Run_Coordination_Meetings:Spring2019_Run
- PrimEx-η run plan
- Production runs, number of triggers
- To join via a Web Browser, go to the page https://bluejeans.com/660743227
Thursday, Feb. 28 at 08:45
- Past 24 hours:
- Beam orbit locks off to allow Hall C current increase
- Unstable beam, lots of tuning to get high current for Hall A/C. 25 trips/hr average and will work to improve when they identify a path forward.
- Compton Production:
- 2.86 billion triggers with Be (Runs 61321-61344)
- 0.24 billion triggers with previous no target (Runs 61308-61311)
- Occupancy plots - Sasha
- Compton plot run 61322 - Drew
- Energy monitoring - Alexandre
- Today (Thursday):
- Remove Be foil @ 8 AM, but leave cylindrical holding tube. Lockup hall at ~1 pm
- Production running with no target until 6 am Friday morning
- Friday plan:
- LHe target installation:
- Hall open at 6 am for bleeding up beamline
- LHe target installation:
Friday, Mar. 1 at 08:45
- Past 24 hours:
- Be target removed Thursday morning
- Examination of material in beamline
- Shift in CompCal acceptance along +x
- FCAL survey from 2015 shows it is shifted in +x direction by 0.53 cm, which matches the shift in CompCal acceptance
- Compton production statistics: summary run list
- 0.24 billion triggers with no target (Runs 61308-61311)
- 2.86 billion triggers with Be (Runs 61321-61344)
- 0.42 billion triggers with empty target holder cylinder (Runs 61345-61354)
- Summary: Empty target is ~25% of statistics for Be target running
- Today's plan:
- LHe target installation (ongoing):
- Hall opened at 6 am for bleeding up beamline and target removal
- Target installation ongoing and S&A to fiducialize and align target around 10 am
- Other work in the Hall:
- Start counter installation status: cabled and signals checked? who?
- Others?
- Empty (evacuated) LHe cell running overnight
- LHe target installation (ongoing):
- LHe target cooldown and filling schedule?
- Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
- Possible plan: Run warm empty target for few shifts, start cooldown over the weekend and fill on Sunday/Monday?
- Plans for next week:
- Beam studies on Monday:
- Parity studies in Hall A from 8:30-12
- Todd will work on improving Hall D optics and convergence from 12-4
- RF recovery on Tuesday: expected but don't know duration yet
- Beam studies on Monday:
Monday, Mar. 4 at 08:45
- Past 72 hours:
- LHe target installation and followup with leak detector
- Accelerator vacuum issue
- Observations with FCAL channels: Suspicious channel in the inner FCAL ring and status from Be running
- Production statistics: summary run list
- 0.86 billion triggers with empty LHe target (61357-61375 (still ongoing))
- Data monitoring and analysis:
- Added CCAL_online plugin to RootSpy
- Empty LHe target runs in PlotBrowser: Any issues observed for other detectors?
- Be target statistics (Ilya)
- CCAL and Be surveys (Sasha)
- Today's plan:
- LHe target vacuum investigation
- Other work in the Hall: FCAL? Others?
- Beam studies complete around noon, back to production if target ready.
- Tomorrow's plan:
- RF recovery expected but don't know duration yet
- Access for other work in Hall? Probably depends on what is found Monday with target.
Tuesday, Mar. 5 at 08:45
- Past 24 hours:
- LHe target vacuum investigation and filling LHe target
- FCAL base replacement
- Accelerator has continuing RF issues maintaining gradient for this beam energy, therefore the energy will be lowered to 11.2 GeV for the remainder of the run.
- Beam could be delivered to Hall D by Thursday day shift at the earliest, but Thursday swing shift more likely.
- Propose to cancel shifts through Thursday owl, and put Thursday day on standby.
- Production statistics: summary run list
- 0.89 billion triggers with empty LHe target (61357-61375)
- 0.45 billion triggers with filled LHe target (61378-61391)
- Issues:
- Improve camera focus on target cart?
- Data monitoring and analysis:
- Rate monitoring (Alexandre)
- Empty and Full LHe target runs in PlotBrowser: Any issues?
- Today's plan:
- RF recovery 8:30 am - 3 pm
- Do we need restricted access for work in the Hall?