Difference between revisions of "September 9, 2019 FCAL Insert Design Meeting"
From GlueXWiki
(→Meeting Time and Place) |
(→Minutes and Action Items) |
||
(6 intermediate revisions by the same user not shown) | |||
Line 30: | Line 30: | ||
* Brass strap soldering progress | * Brass strap soldering progress | ||
− | == Minutes == | + | == Minutes and Action Items == |
+ | |||
+ | * Discussed the center support tube | ||
+ | ** Need to determine material for center tube - Sasha | ||
+ | *** consider magnetic properties, thermal conductivity, strength, stiffness | ||
+ | ** Need to determine the maximum hole size allowable (assume steel initially) - Tim | ||
+ | ** Need to move the upstream end flush with US side of acrylic sheet - Keith | ||
+ | ** Need to decide on size of hole (2x2 crystals now) - Sasha | ||
+ | * Discussed Monitoring system | ||
+ | ** Use 1/2" acrylic sheet same as FCAL | ||
+ | ** Discussed possibility of pre-assembling the acrylic, fibers and rohacell | ||
+ | ** Determine diameter of fibers - Sasha | ||
+ | ** Layout fibers coming through rohacell and cut angles on acrylic - Keith/Tim | ||
+ | ** Add fibers to inner hole edge | ||
+ | ** Fabricate a test piece - Tim/Keith/Josh | ||
+ | * Discussed feedthru panels attached to cable support chains | ||
+ | ** Cables are stiff, ok to attach panels to cables with hinge | ||
+ | ** Use ComCal feedthu sizing to develop panels - Keith | ||
+ | ** Cables should be strain relived to chains | ||
+ | * Discussed cooling system | ||
+ | ** Concept to glue copper tubes to aluminum blocks with thermally conductive epoxy accepted | ||
+ | ** Concept to clamp cooling plates to inner support tube accepted | ||
+ | ** Assuming 2.1KW total heat load, we would need 2 of the chillers used for BCAL. | ||
+ | ** Continue with connections and manifold layou - Keith/Tim | ||
+ | * Discussed Brazing of PMT module straps and new mag field tests | ||
+ | ** Josh has successfully brazed and cleaned (warm water) an assembly and is testing | ||
+ | ** Test with 2mm cookie to ensure enough pressure can be maintained for good transmission - Josh | ||
+ | ** Sasha wishes to assemble a new 9 module array for magnetic field testing | ||
+ | *** 18mm diameter light guides are needed - Tim | ||
+ | *** 6mm longer with 50 micron larger ID mag shield steel needed - Tim | ||
+ | *** additional mu metal shields needed (same as previous - 350 microns) - Tim | ||
+ | *** Have steel shields annealed - Tim | ||
+ | * Discussed test fixutre for PMTs in beam | ||
+ | ** Need to fabricate steel case - Tim | ||
+ | ** need to fabricate support structure - Tim | ||
+ | ** Need to fabricate feedthru panel - Josh/Tim | ||
+ | ** need to fabricated aluminum base plate - Josh/Tim | ||
+ | ** | ||
== Action items == | == Action items == |
Latest revision as of 10:31, 16 September 2019
Meeting Time and Place
Monday Sept 9 2pm At Jefferson Lab, room TED 2504
- Present - Sasha Somov, Josh Crafts, Vlad, Eugene, Stephanie, Keith Harding, Tim
Agenda
- Discuss 40x40 crystal assembly with 19 Lead glass modules around
- Crystals move to 12.5 cm from US face of lead glass
- 40x40 crystal matrix starts with shim to be able to go to 32x32 fairly easy.
- Decision to pre-measure stacks of crystals and the existing FCAL to determine bottom row offsets
- Discuss installing Rohacel US of crystals to fill hole and support the lead glass blocks
- Rohacel properties Media:Rohacel cut sheet.pdf
- Radiation Hardness https://p25ext.lanl.gov/phenix/mvd/notes/1997/PHENIX-MVD-97-5/radiation.html
- http://www.phenix.bnl.gov/WWW/publish/bosze/phenixnote272/radiation.html (same data)
- Discuss Tungsten absorber
- Cover 1.5 crystals ok?
- Rohacell supported
- Monitoring System
- Use Acrylic sheet, how thick?
- How to attach fibers?
- Cooling of blocks - 2.1 KW needed
- 2 Chillers like those used for BCAL ($16K ea)
- 4 water to air Heat exchangers around crystal area
- 9 parallel circuits for each chiller
- potted copper tube into aluminum blocks
- Cooling of inner tube - removeable plate
- electronics patch panels DS of crystal pmts
- Brass strap soldering progress
Minutes and Action Items
- Discussed the center support tube
- Need to determine material for center tube - Sasha
- consider magnetic properties, thermal conductivity, strength, stiffness
- Need to determine the maximum hole size allowable (assume steel initially) - Tim
- Need to move the upstream end flush with US side of acrylic sheet - Keith
- Need to decide on size of hole (2x2 crystals now) - Sasha
- Need to determine material for center tube - Sasha
- Discussed Monitoring system
- Use 1/2" acrylic sheet same as FCAL
- Discussed possibility of pre-assembling the acrylic, fibers and rohacell
- Determine diameter of fibers - Sasha
- Layout fibers coming through rohacell and cut angles on acrylic - Keith/Tim
- Add fibers to inner hole edge
- Fabricate a test piece - Tim/Keith/Josh
- Discussed feedthru panels attached to cable support chains
- Cables are stiff, ok to attach panels to cables with hinge
- Use ComCal feedthu sizing to develop panels - Keith
- Cables should be strain relived to chains
- Discussed cooling system
- Concept to glue copper tubes to aluminum blocks with thermally conductive epoxy accepted
- Concept to clamp cooling plates to inner support tube accepted
- Assuming 2.1KW total heat load, we would need 2 of the chillers used for BCAL.
- Continue with connections and manifold layou - Keith/Tim
- Discussed Brazing of PMT module straps and new mag field tests
- Josh has successfully brazed and cleaned (warm water) an assembly and is testing
- Test with 2mm cookie to ensure enough pressure can be maintained for good transmission - Josh
- Sasha wishes to assemble a new 9 module array for magnetic field testing
- 18mm diameter light guides are needed - Tim
- 6mm longer with 50 micron larger ID mag shield steel needed - Tim
- additional mu metal shields needed (same as previous - 350 microns) - Tim
- Have steel shields annealed - Tim
- Discussed test fixutre for PMTs in beam
- Need to fabricate steel case - Tim
- need to fabricate support structure - Tim
- Need to fabricate feedthru panel - Josh/Tim
- need to fabricated aluminum base plate - Josh/Tim