Difference between revisions of "August 26, 2021 CPP Design Meeting"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 10: | Line 10: | ||
* Design/Fab/Procurement status | * Design/Fab/Procurement status | ||
** Installation/assy 3D Model and dwgs | ** Installation/assy 3D Model and dwgs | ||
− | ** Stand [[ | + | ** Stand [[image:cpp_stand.pdf|thumb]] |
− | ** Steel | + | ** Steel [[media:cpp_stand.pdf|thumb]] |
** Fcal platform mods | ** Fcal platform mods | ||
*** Cutouts complete [[image:cpp_cutout.pdf|thumb]] | *** Cutouts complete [[image:cpp_cutout.pdf|thumb]] |
Revision as of 16:43, 25 August 2021
Meeting Time and Place
Thursday August 26, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/July_15,_2021_CPP_Design_Meeting
- Testing status - Beni
- Design/Fab/Procurement status
- Installation/assy 3D Model and dwgs
- Stand
- Steel thumb
- Fcal platform mods
- Cutouts complete
- Most holes drilled in floor
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis - approved by Tom Renzo - need to release into system
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
- CPP Detector operations in Hall D OSP
- Possible use of nitrogen flow for cooling electronics in Faraday cage