Difference between revisions of "JEF meeting, January 14, 2022"
From GlueXWiki
(Created page with "=Meeting time and location= *9:30 am EST (JLab time) remote only *Zoom meeting ID: [https://jlab-org.zoomgov.com/j/1610509142?pwd=STNZUmNoMElqbHRVdjlVb0ZzR1piZz09 161 050 9142...") |
|||
Line 10: | Line 10: | ||
* Data analysis | * Data analysis | ||
* Simulations | * Simulations | ||
+ | |||
+ | =Minutes= | ||
+ | Attendees: Igal,Bill,Phil,Jon,Sasha,Liping,Tim B.,Azizah,Olga,S.T. | ||
+ | * Sasha and Liping met with SICCAS last week | ||
+ | ** SICCAS still have quality control problems with lead oxide powder | ||
+ | ** SICCAS have been able to grow some crystals -- plan to send us ~100 in March? (plan for Jane to do preliminary QA) | ||
+ | * PMTs continue arriving at lab at steady pace | ||
+ | * Manpower: Sasha in contact with Patrizia -- detector support group potentially on board | ||
+ | ** Igor and Phil could potentially provide undergrad students, but not clear these students would be allowed on site | ||
+ | ** GWU could work on producing silicon cookies | ||
+ | ** GWU, UNCW could work on PMT tests (Sasha working on paperwork for long term loans to GWU) | ||
+ | ** Tim B. floated idea to have URegina students be sent to UNCW | ||
+ | * Fernando producing design for PMT base -- version to check week of 1/17? (~5 dividers) | ||
+ | ** Thinking about beam tests during CPP/PrimEx runs | ||
+ | * Arshak working on cleaning up fabrication lab, start to build modules soon? (Also working on LMS) | ||
+ | * Second plate for installing 12 modules on PS arm in the works | ||
+ | * Frame design in fairly good shape already, planning meeting in 2 weeks? |
Revision as of 08:54, 18 January 2022
Meeting time and location
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- SICCAS crystals
- Module fabrication
- Light Monitoring System
- COMCAL tests, TAC running, etc.
- Data analysis
- Simulations
Minutes
Attendees: Igal,Bill,Phil,Jon,Sasha,Liping,Tim B.,Azizah,Olga,S.T.
- Sasha and Liping met with SICCAS last week
- SICCAS still have quality control problems with lead oxide powder
- SICCAS have been able to grow some crystals -- plan to send us ~100 in March? (plan for Jane to do preliminary QA)
- PMTs continue arriving at lab at steady pace
- Manpower: Sasha in contact with Patrizia -- detector support group potentially on board
- Igor and Phil could potentially provide undergrad students, but not clear these students would be allowed on site
- GWU could work on producing silicon cookies
- GWU, UNCW could work on PMT tests (Sasha working on paperwork for long term loans to GWU)
- Tim B. floated idea to have URegina students be sent to UNCW
- Fernando producing design for PMT base -- version to check week of 1/17? (~5 dividers)
- Thinking about beam tests during CPP/PrimEx runs
- Arshak working on cleaning up fabrication lab, start to build modules soon? (Also working on LMS)
- Second plate for installing 12 modules on PS arm in the works
- Frame design in fairly good shape already, planning meeting in 2 weeks?