Line 33: | Line 33: | ||
#* (U1-10-TOP MPOD crate) | #* (U1-10-TOP MPOD crate) | ||
#Plans | #Plans | ||
− | #*No beam from 6:30am until sometime after 3pm, power shedding. | + | #*No beam from 6:30am until sometime after 3pm, likely 5pm+ due to power shedding. |
#*Walk-through at 11am | #*Walk-through at 11am | ||
+ | #*Site exit opposite Tech Center closed most of the day. | ||
#Commissioning steps temporarily postponed: | #Commissioning steps temporarily postponed: | ||
#*Flux optimization/Act .Col. calibration | #*Flux optimization/Act .Col. calibration | ||
#*Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help. | #*Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help. |
Revision as of 08:11, 23 June 2022
↑ Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Thursday June 23
- Last 24h:
- Inadvertent change to tagger magnet settings backed out
- Target moved out
- Richard took the microscope scan data
- Bleedthrough beam current was very low
- Thunderstorms made TAC run impossible.
- Sasha configured the trigger for straight track running
- Beam back near midnight but ran into DAQ problems.
- Overnight empty target production
- Shift Summaries
- Reports
- Issues
- DAQ crash ROCTRIG2 - called Sergey
- DAQ lost comms with ROCBCAL11 - stop & restart DAQ fixed this
- AD00C x position moving
- (Tagger NMR)
- (DIRC sensor)
- (DAQ livetime)
- (Beam position stability)
- (U1-10-TOP MPOD crate)
- Plans
- No beam from 6:30am until sometime after 3pm, likely 5pm+ due to power shedding.
- Walk-through at 11am
- Site exit opposite Tech Center closed most of the day.
- Commissioning steps temporarily postponed:
- Flux optimization/Act .Col. calibration
- Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.