* FastTrack schedule status - George, Chuck | * FastTrack schedule status - George, Chuck | ||
− | * | + | * Direct EPICS to Ethernet/IP communications - Elliott |
+ | * Status of PLC programming - Mark W | ||
* Moving power supply dump resistor - Mark S | * Moving power supply dump resistor - Mark S | ||
* Ethernet vs ControlNet and A-B Point I/O order - Elliott | * Ethernet vs ControlNet and A-B Point I/O order - Elliott | ||
+ | * QWeak area, bigger door in F117 - Tom | ||
* Two coils per A-B chassis? - Scot | * Two coils per A-B chassis? - Scot | ||
* Ordering remaining controls instrumentation and components - Scot, Elliott | * Ordering remaining controls instrumentation and components - Scot, Elliott |
Revision as of 10:23, 16 December 2009
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 17-Dec-2009 9:45 am ARC 428
Agenda
- FastTrack schedule status - George, Chuck
- Direct EPICS to Ethernet/IP communications - Elliott
- Status of PLC programming - Mark W
- Moving power supply dump resistor - Mark S
- Ethernet vs ControlNet and A-B Point I/O order - Elliott
- QWeak area, bigger door in F117 - Tom
- Two coils per A-B chassis? - Scot
- Ordering remaining controls instrumentation and components - Scot, Elliott
- Wiring progress in F117 - Scot
- Status of interface to cryo can - George
- Status of pressure relief system design - George
- Status of ordering cryo can - George
- PLC programming and testing - Mark W
- Coil 1 modification and testing - George
- Coil 2 cost and schedule - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails and transportainer from IUCF - Chuck
- Safety reviews: when to start formal process - George, Elliott
- 5 G contours - George
- Coil Test Top To-Do items