Line 13: Line 13:
 
* Wiring completion date and moving into Test Lab - all
 
* Wiring completion date and moving into Test Lab - all
 
** when do we need the hole in the wall?
 
** when do we need the hole in the wall?
* What additional computers are needed? - all
 
* Analog output module to control new valve - Elliott
 
 
* Safety review and progress towards getting OSP and COO - Elliott, Josh, Tim
 
* Safety review and progress towards getting OSP and COO - Elliott, Josh, Tim
 
** OSP writing assignments and subject matter experts
 
** OSP writing assignments and subject matter experts
Line 22: Line 20:
 
* EPICS connection to PLC - Elliott, Wesley
 
* EPICS connection to PLC - Elliott, Wesley
 
* Status of PLC programming - Mark W
 
* Status of PLC programming - Mark W
** RS232 Point I/O module restrictions
 
 
** Lakeshore calibrations
 
** Lakeshore calibrations
 
* Wiring progress in F117 - Scot
 
* Wiring progress in F117 - Scot

Revision as of 14:13, 23 April 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 19-Apr-2010 9:30am ARC 428


Agenda

  • Controlling new valve - Elliott
  • Response to Lehman review questions - George
  • Wiring completion date and moving into Test Lab - all
    • when do we need the hole in the wall?
  • Safety review and progress towards getting OSP and COO - Elliott, Josh, Tim
    • OSP writing assignments and subject matter experts
    • P&I and wiring diagrams, machine protection diagrams, failure scenario analysis
  • HMI and EWEB programming, UPS, terminal server, etc. - Yi, Elliott
  • What PLC display pages are needed (HMI and web) - Josh
  • EPICS connection to PLC - Elliott, Wesley
  • Status of PLC programming - Mark W
    • Lakeshore calibrations
  • Wiring progress in F117 - Scot
  • Progress towards testing PLC program in 101 and F117 - Mark W, Scot, Mark S
  • Parts orders, installation progress - George
  • Coil 1 repair status - George
  • Coil 2 repair status - George
  • Coil 3 progress at IUCF - George
  • Coil 4 repair status - George