Line 12: | Line 12: | ||
* DOE: new soleniod vs new coils and Helium vessels - George | * DOE: new soleniod vs new coils and Helium vessels - George | ||
* Update on safety interlock design - Mark S, Scot | * Update on safety interlock design - Mark S, Scot | ||
+ | ** changes to fast and slow dump circuits | ||
+ | ** redundancy in power supply overcurrent interlock | ||
* Update on magnet power supply commissioning - Cody | * Update on magnet power supply commissioning - Cody | ||
* Update on EPICS <--> PLC communications - Wesley | * Update on EPICS <--> PLC communications - Wesley | ||
Line 23: | Line 25: | ||
** when does the PLC need to move to F117? | ** when does the PLC need to move to F117? | ||
** can Wesley and Cody play a major role in commissioning the control system? | ** can Wesley and Cody play a major role in commissioning the control system? | ||
+ | ** can we use the power supply analog current output signal? | ||
* PLC programming status - Mark W | * PLC programming status - Mark W | ||
** C-glass calibrations - George | ** C-glass calibrations - George |
Latest revision as of 15:29, 26 May 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 27-May-2010 9:30am ARC 428
Agenda
- Coil test plan - George, Josh
- DOE: new soleniod vs new coils and Helium vessels - George
- Update on safety interlock design - Mark S, Scot
- changes to fast and slow dump circuits
- redundancy in power supply overcurrent interlock
- Update on magnet power supply commissioning - Cody
- Update on EPICS <--> PLC communications - Wesley
- Magnetic field near control racks and computers - George
- Safety review - OSP and COO - Elliott, Josh, Tim
- meeting with Bob May et al. next week
- Final (I hope) A-B equipment order - Elliott
- RS232 module, 4-chan 4-20 mA output module, two carriers
- Wiring and testing controls racks - Scot
- how do we test the system in F117?
- when does the PLC need to move to F117?
- can Wesley and Cody play a major role in commissioning the control system?
- can we use the power supply analog current output signal?
- PLC programming status - Mark W
- C-glass calibrations - George
- RS485 vs RS422 - Mark W, Elliott
- HMI and EWEB programming - Yi, Elliott
- offsite visibility of EWEB pages
- Installation status - George
- Coil repair status - George