Difference between revisions of "Aug 16, 2011 SiPM Electrical and Cooling"

From GlueXWiki
Jump to: navigation, search
(Created page with "== Action Items from previous meetings == # Develop front and back views of jumper sheets. (Jack) #* This specifically includes the settings for the pre-production boards that ...")
 
(Action Items from previous meetings)
Line 1: Line 1:
 
== Action Items from previous meetings ==
 
== Action Items from previous meetings ==
  
# Develop front and back views of jumper sheets.  (Jack)
 
#* This specifically includes the settings for the pre-production boards that are needed by Wed of next week.
 
 
# Test wrapping forms (Elton)
 
# Test wrapping forms (Elton)
# Order glue (and any other consumables) to glue light guides (Scot)
 
# Check new gluing jig for the light guides (Scot and Jim)
 
  
 
== Tentative Agenda ==
 
== Tentative Agenda ==

Revision as of 17:54, 9 August 2012

Action Items from previous meetings

  1. Test wrapping forms (Elton)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (everyone)
    • SiPMs assignment for new boards
  5. Mechanical assembly (Jim)
  6. Temperature compensation (Jack)
  7. Electronic boards (Chris)
  8. Light guide gluing setup (Scot via e-mail)

Minutes

Attending: