== Production == | == Production == | ||
− | - Dave: Two wire planes have been deadened, two more remaining. The filed wire | + | - Dave for the spare package: Two wire planes (#2 and #3) have been deadened, two more remaining. The filed wire on #2 was fixed (broke during deadening). It turned out we don't have enough HV cables (short cables with male connectors) that are soldered on the wired frames, and we have order them. This is because we originally planned for 4 spare cells. |
− | - Package #3 repair: | + | - Package #3 repair: the three field wires on the wire frame of cell #6 were fixed and on Monday we install the sixth cell on the package upside-down. We ended up holding the spacer ring with fingers |
== Installation == | == Installation == |
Revision as of 16:00, 11 April 2013
April 11, 2013 FDC meeting
Agenda
- Production Construction Tracking (Dave)
- Package #3 repair
- Installation (Lubomir, Bill)
- Channel assignment: rack's side (Fernando), signal cables detector side (Vlad's scheme), LV cables detector side (Vlad's scheme)
- Schedule latest version
- Plans for practicing at Blue Crab
- Engineering (Bill)
- Cooling system tests
- Electronics (Chris, Nick)
- Tests at EEL126 FDC E-log (Beni)
- Other