Difference between revisions of "Minutes-6-26-2014"
From GlueXWiki
Line 22: | Line 22: | ||
= Minutes = | = Minutes = | ||
− | Participants: | + | Participants: Naomi (CMU), Curtis, Dave, Beni, Chris, Nick, Simon, Bill, Fernando, Eugene, and Lubomir (JLab). |
+ | |||
+ | == Readiness review == | ||
+ | |||
+ | - Curtis prepared (Elton requested) a draft of a commissioning plan for the CDC (linked above). Lubomir and Beni will do the same for the FDC. It doesn't have to be a final version. All the other documents needed for the review are ready. | ||
+ | |||
+ | == Gas system == | ||
+ | |||
+ | - On Wednesday Scott replaced quickly under pressure, the relief valves on the two mixing tanks (first picture). | ||
== Electronics == | == Electronics == |
Revision as of 16:16, 26 June 2014
June 26, 2014 FDC+CDC meeting
Agenda
- Readiness review (Beni, Lubomir)
- Gas system [1], [2]
- DAQ (Beni)
- CDC status (Beni)
- noise studies
- Electronics (Chris, Nick)
- Engineering (Bill)
- FDC chiller [3]
- Other