Difference between revisions of "Photon Beam Commissioning Discussion Aug 13, 2014"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 27: | Line 27: | ||
#* Need signed document? | #* Need signed document? | ||
#* Accelerator and Hall D Interface Document - needs to be finalized. | #* Accelerator and Hall D Interface Document - needs to be finalized. | ||
− | # Electron Commissioning (Todd/Mike) | + | # Update on Electron Commissioning (Todd/Mike) |
− | # Photon Commissioning | + | # Update on Photon Commissioning (Alexandre) |
− | # Radiation monitors and controls (Pavel) | + | #* Version for the ARR |
+ | # Update Radiation monitors and controls (George/Pavel) | ||
# Other business | # Other business | ||
Revision as of 17:47, 8 August 2014
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
Action Items
- Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Sasha defined geometry, Richard will add field map
- Sasha needs to update geometry with girder.
- Richard has not had time to add Dan's new field. For now use the old field.
- Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Eugene, Alexandre for Hall D)
- Need rates for profiler, start counter, ps
Agenda
- Announcements
- Debrief Aug 8 Review:
- Photon Beam Commissioning Review Page
- Comments / to-do-list for ARR
- ARR presentations
- Electron Beam Specifications
- Need signed document?
- Accelerator and Hall D Interface Document - needs to be finalized.
- Update on Electron Commissioning (Todd/Mike)
- Update on Photon Commissioning (Alexandre)
- Version for the ARR
- Update Radiation monitors and controls (George/Pavel)
- Other business
Minutes
Attending: