=== Trigger Commissioning Plan ===
 
=== Trigger Commissioning Plan ===
  

Revision as of 17:18, 14 September 2014

Trigger Commissioning Plan

Phase 1: Photon-beam Commissioning

  • PS stand alone trigger (2 - 3 days)
-- trigger with PSC
-- read out PS and PSC
-- trigger distribution through GTP. Use PCS self trigger if problems with GTP