Difference between revisions of "September 22, 2014"

From GlueXWiki
Jump to: navigation, search
Line 1: Line 1:
 
[https://halldweb1.jlab.org/wiki/index.php/Trigger_Commissioning Trigger Commissioning Plan]
 
[https://halldweb1.jlab.org/wiki/index.php/Trigger_Commissioning Trigger Commissioning Plan]
 +
  
 
* CTP installation and testing
 
* CTP installation and testing
Line 5: Line 6:
 
* Test of the global trigger distribution (using BCAL north crates)
 
* Test of the global trigger distribution (using BCAL north crates)
  
*: Global energy sum
+
:* Global energy sum
  
 
*: BCAL cosmic trigger
 
*: BCAL cosmic trigger

Revision as of 09:49, 22 September 2014

Trigger Commissioning Plan


  • CTP installation and testing
  • Test of the global trigger distribution (using BCAL north crates)
  • Global energy sum
  • BCAL cosmic trigger
  • BCAL cosmic trigger for FDC / CDC
  • Trigger calibration status from sub-detectors
  • TAGM/TAGH setups
  • Start Counter
  • Pair Spectrometer
  • Trigger monitoring