Difference between revisions of "Testing High Granularity Hodoscope"
From GlueXWiki
(→Test Data) |
(→Procedure) |
||
Line 8: | Line 8: | ||
<br> | <br> | ||
<br> | <br> | ||
+ | 1. Connect the 37 pin power cable to the WIENER 8008 power supply slot 2, CH 0-3. | ||
+ | 2. Connect the redl Bias cable to the iSEG module slot 1, ch 0-15. | ||
+ | 3. Turn on the WEINER MPOD main power stitch. | ||
+ | 4. Open iSEG SNMP Control Version 1.1.5.0 software. | ||
+ | 5. In the <B> File Menu</b>, click select controller and use the following IP address: | ||
+ | *192.168.0.0 | ||
+ | 6. The software will populate the currently loaded iSEG module and 8008 module. | ||
==Testing Silicon Photomultipliers== | ==Testing Silicon Photomultipliers== |
Revision as of 13:46, 17 June 2015
Procedure
Low Voltage/ Bias Control
In preparation for the tests, set-up the WIENER power supply (readout power and bias supplies) under computer control.
The readout supplies (channels 0 and 1 of the 8008L module) should be set to 5V and the bias supplies (channels 0 through 4 of the ISEG module)
should be set to the respective bias operating voltages from the SiPM channel chart.
1. Connect the 37 pin power cable to the WIENER 8008 power supply slot 2, CH 0-3. 2. Connect the redl Bias cable to the iSEG module slot 1, ch 0-15. 3. Turn on the WEINER MPOD main power stitch. 4. Open iSEG SNMP Control Version 1.1.5.0 software. 5. In the File Menu, click select controller and use the following IP address: *192.168.0.0 6. The software will populate the currently loaded iSEG module and 8008 module.
Testing Silicon Photomultipliers
Layout
Test Data
File:SiPM 3mm - PS-2015TestResult.xlsx