Difference between revisions of "June 14, 2016"

From GlueXWiki
Jump to: navigation, search
Line 6: Line 6:
 
* CTP, SSP firmware update
 
* CTP, SSP firmware update
 
:: Update CTP firmware on tagh1 crate, check performance using play back
 
:: Update CTP firmware on tagh1 crate, check performance using play back
 +
 +
* High-rate trigger performance testing
  
 
* Study L1 trigger performance for spring 2016 runs:
 
* Study L1 trigger performance for spring 2016 runs:

Revision as of 12:23, 14 June 2016

  • FADC 250 firmware update
Check performance using test vector (new firmware installed on rocfcal1, rocbcal7)
Update config files, new parameters
  • CTP, SSP firmware update
Update CTP firmware on tagh1 crate, check performance using play back
  • High-rate trigger performance testing
  • Study L1 trigger performance for spring 2016 runs:
- L1 online monitoring plugin
monitoring fadc250 in mode 7
- Trigger emulation
- Efficiency studies (TAGH & ST)
- Compare performance with MC predictions
  • Trigger simulation
Trigger parameters in DL1Trigger bank
Trigger simulation factory
Efficiency/rate studies. Compare with hardware performance
  • L1 hardware monitoring
  • Add more features to SYNC events




L1 online monitor (mode 7)

  • Trigger parameters in RCDB, interface with GlueX reconstruction
  • Commissioning FCAL & BCAL trigger
Adjusting timing offsets
Masked rings in the FCAL
  • Short term plans