Difference between revisions of "Online Action Items"
From GlueXWiki
m |
|||
Line 6: | Line 6: | ||
==Action Items In Progress - Short Term== | ==Action Items In Progress - Short Term== | ||
+ | * Query collaboration concerning short and long-term notebook/logbook needs and requirements - Elliott, 12-Nov-2008 | ||
* Use full-scale FDC test as testbed for controls system - Elliott, 31-Jan-2008 | * Use full-scale FDC test as testbed for controls system - Elliott, 31-Jan-2008 | ||
** Developing initial test system in DAQ lab instead- Elliott, Vardan, Feb 2008 | ** Developing initial test system in DAQ lab instead- Elliott, Vardan, Feb 2008 |
Revision as of 12:50, 13 November 2008
Contents
Open Action Items
- Determine requirements for and set up CODA-based Electronics group test stands - Elliott W, Chris C, Dave A, 9-Aug-2007
Action Items In Progress - Short Term
- Query collaboration concerning short and long-term notebook/logbook needs and requirements - Elliott, 12-Nov-2008
- Use full-scale FDC test as testbed for controls system - Elliott, 31-Jan-2008
- Developing initial test system in DAQ lab instead- Elliott, Vardan, Feb 2008
Action Items In Progress - Long Term
- Revisit energy-sum trigger algorithm - Alex S - 29-Nov-2007
- CNU algorithm needs updating to include all backgrounds
Action Items on Hold
- Complete Trigger/DAQ/Monitoring/Controls work breakdown - Elliott, 9-Aug-2007
- Form FCAL test subgroup and plan 2008 FCAL test - Elliott, 4-Oct-2007
- Not clear if and when test will happen given new accelerator schedule - Elliott, 16-Jan-2008
Completed Action Items
- Determine expected average event size - Alex, Eugene, Elliott, David, Fernando, Nov-2007 - completed May-2008
- Add electronics design goals and milestones to wiki pages - Fernando, 15-Dec-2007 - completed Mar-2008
- Complete Monitoring/Controls milestones - Elliott, 19-Jul-2007, completed Feb 2008
- Generate information for Elke's Action Item Tracker based on Online Major Milestones - Elliott, 15-Dec-2007, completed Jan-2008
- Derive manpower requirements from Trigger/DAQ milestones - Elliott and Graham, 15-Dec-2007, completed by Elke Dec-2007
- Design document listing basic requirements and design goals - Elliott, 19-Jul-2007, completed 15-Dec-2007
- Combine and reconcile DAQ and Hall D milestones - Elliott and Graham, 29-Nov-2007, completed 15-Dec-2007
- Milestones from JLab DAQ group - Graham H, 19-Jul-2007, completed 29-Nov-2007
- DAQ board specifications needed by Electronics group - Dave A, 9-Aug-2007, completed 15-Oct-2007
- Form committee to lead effort to determine event size - Elliott, 29-Aug-2007, completed 20-Sep-2007
- Trigger/DAQ milestones - Elliott, 19-Jul-2007, completed 15-Aug-2007
- Create task-oriented list of OWG responsibilites instead of existing group-oriented list - Elliott, 15-Jun-07, superceded 9-Aug-2007
- Instead, create work breakdown in Contractor - 9-Aug-2007
- Replace "GlueX" with "Hall D" in wiki pages - Elliott, 15-Jun-07, completed 20-Jun-07