Difference between revisions of "July 12, 2018 DIRC"
From GlueXWiki
(Created page with "== Meeting Information == GlueX DIRC Meeting<br> Thursday July 12, 2018<br> 10:00 am, EDT<br> JLab room A110<br> == Connection Using Bluejeans == # To join via Polycom room...") |
(→Agenda) |
||
Line 17: | Line 17: | ||
# Announcements | # Announcements | ||
+ | #* Documentation wiki page [[DIRC]] | ||
# Bar box transportation and installation: plans for a writeup? (Matt, et al.) | # Bar box transportation and installation: plans for a writeup? (Matt, et al.) | ||
# Optical box | # Optical box | ||
#* Water quality plan (Tim, et al.) | #* Water quality plan (Tim, et al.) | ||
− | |||
− | |||
− | |||
#* Fabrication status update (Ernie and Jason) | #* Fabrication status update (Ernie and Jason) | ||
#** Box production at Lesker: delivery date to Bates? | #** Box production at Lesker: delivery date to Bates? | ||
− | #** PMT test fixture and cookies ( | + | #** PMT test fixture and cookies (Maria) |
#** Window procurement | #** Window procurement | ||
#** Dark box design | #** Dark box design |
Revision as of 12:05, 11 July 2018
Meeting Information
GlueX DIRC Meeting
Thursday July 12, 2018
10:00 am, EDT
JLab room A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcements
- Documentation wiki page DIRC
- Bar box transportation and installation: plans for a writeup? (Matt, et al.)
- Optical box
- Water quality plan (Tim, et al.)
- Fabrication status update (Ernie and Jason)
- Box production at Lesker: delivery date to Bates?
- PMT test fixture and cookies (Maria)
- Window procurement
- Dark box design
- Air flow considerations and plan:
- The power dissipated by each module is ~4 Watts, so the total in one optical box enclosure would be ~144 W.
- Temperature and flow rate requirements?
- Air flow considerations and plan:
- DIRC installation schedule
- DIRC BBox Split Flange Seal
- Simulation studies (Maria and Roman)
- MAPMT testing (Bill and Andrew)
- Magnetic field test
- Commissioning plans
- Reminder: Addressing ERR review recommendations
- Recommendations pertaining to Fall 2018 DIRC commissioning should be addressed by August 20 (close of Hall D for beam)
- AOB