Difference between revisions of "Run Planning Meeting Notes, Feb. 14-Fev 21, 2019"
From GlueXWiki
(→Thursday, Feb. 14 at 08:45) |
(→Thursday, Feb. 14 at 08:45) |
||
Line 12: | Line 12: | ||
#** DAQ stopped twice due to the out of sync issue. | #** DAQ stopped twice due to the out of sync issue. | ||
#* Tagger RF time: | #* Tagger RF time: | ||
+ | https://logbooks.jlab.org/entry/3652533 | ||
+ | #*Today: | ||
+ | #** No planned access | ||
+ | #** Opportunistic access requested by Kenoe to work on GEM. | ||
== Friday, Feb. 15 at 08:45 == | == Friday, Feb. 15 at 08:45 == |
Revision as of 09:39, 14 February 2019
Thursday, Feb. 14 at 08:45
- Past 24 hours:
- Acceptable quality beam established early morning around 11:00 am.
- Beam profile and convergence by Jay:https://logbooks.jlab.org/entry/3652506
- DIRC data taking.
- Acceptable quality beam established early morning around 11:00 am.
- Issues
- Cryo Water Temperature jump to 72F (limit 70F).
- Due to pump switch: https://logbooks.jlab.org/entry/3652512
- IOC lost communication
- IOCHDCOL failed at 21:30. Reported to us by MCC at 0:00. Reset at 1:50 am. Hovanes verified things are ok at 3am. https://logbooks.jlab.org/entry/3652920
- DIRC SSP problem:
- DAQ stopped twice due to the out of sync issue.
- Tagger RF time:
- Cryo Water Temperature jump to 72F (limit 70F).
https://logbooks.jlab.org/entry/3652533
- Today:
- No planned access
- Opportunistic access requested by Kenoe to work on GEM.
- Today: