Difference between revisions of "Construction plan 1/1/2020 - 30/8/2020"
From GlueXWiki
Line 26: | Line 26: | ||
:: - Tool in preparation | :: - Tool in preparation | ||
:: - Mix RTV | :: - Mix RTV | ||
− | :: - | + | :: - Pour to the gluing fixture |
+ | :: - wait 1 day to set, move to the oven for several hours | ||
+ | :: - Time: 2-3 days per 30 cookies | ||
* Module fabrication | * Module fabrication | ||
:: | :: |
Revision as of 19:27, 8 January 2020
The goal is to assemble 450 - 500 modules by the end of summer
- Brazing straps
- Procedure - brazing setup exists, has to be finalized
- Time per module - 30 min
- ESR shaping
- - ESR cutting (cutting tool exist)
- - Shaping in the oven (2 shaping tools exist, 30 min per cycle]
- Tedlar cutting
- - Tool exists
- - Time per module - 15 min
- Crystal wrapping
- - Tool exists
- - Time per module - 20 min
- Preparation of silicon cookie
- - Tool in preparation
- - Mix RTV
- - Pour to the gluing fixture
- - wait 1 day to set, move to the oven for several hours
- - Time: 2-3 days per 30 cookies
- Module fabrication