Difference between revisions of "Run Planning Meeting Notes, August 13 -17, 2020"
From GlueXWiki
(→Thursday, August 13) |
(→Thursday, August 13) |
||
Line 14: | Line 14: | ||
#* DIRC LV tripped due to the cur off during night | #* DIRC LV tripped due to the cur off during night | ||
# Run Plan | # Run Plan | ||
− | #* Production | + | #* Production |
− | #* | + | #* Hall C path change tentatively at August 24th. Impact initial 3 days of running without orbit lock, 350nA beam will trip AD00. |
+ | #* CPP installation: | ||
+ | #** CPP's preference: schedule the CPP test after Aug 21. | ||
+ | #** Installation to be completed during the next maintenance day. Date undecided, Jay will inform me as soon as he decided. | ||
# Pending issues: | # Pending issues: | ||
− | #* TagM card | + | #* TagM card issue. |
Revision as of 08:08, 13 August 2020
<- Back to Run Coordination Meetings:Summer2020
Thursday, August 13
- Last 24 hours
- Diamond alignment completed by Hovanes during his shift
- TAGH scan completed by Sasha during his shift
- Reports/Issues
- Monitoring link (Twice a day monitoring line) is slow last night.
- DIRC LV tripped due to the cur off during night
- Run Plan
- Production
- Hall C path change tentatively at August 24th. Impact initial 3 days of running without orbit lock, 350nA beam will trip AD00.
- CPP installation:
- CPP's preference: schedule the CPP test after Aug 21.
- Installation to be completed during the next maintenance day. Date undecided, Jay will inform me as soon as he decided.
- Pending issues:
- TagM card issue.