Difference between revisions of "July 01, 2021 CPP Design Meeting"
From GlueXWiki
(→Meeting Time and Place) |
(→Minutes and Action Items) |
||
Line 25: | Line 25: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
+ | * Rory discussed the importance of making sure the downstream detector has it's x-ray port facing downstream for access. With this in mind the 2 vertical downstream detectors will need to have a gap in between to accommodate the HV cables protruding past the planes. The x-ray port will be 15inches from the center of the detector | ||
+ | * Elton will label the detectors as the testing goes along to ensure we know what detector is installed where | ||
+ | * Discussed OSP - | ||
+ | ** Beni put the OSP on the table for reading and signatures. He will need a table to put the chambers on | ||
+ | ** Need scintillator paddles in the EEL 126 | ||
+ | ** Need to hook up gas to the detector being tested first | ||
+ | * There will be a 10" vacuum tube installed DS of the detector | ||
+ | * 2 scintillator paddles will be installed vertically on the DS end of the detector close to the beam maybe 10" from the center | ||
+ | * We discussed the clearance for the SHV connectors and using a right angle connector. Stephanie reminded us that we had made clearance in the base to allow room for the straight connector. | ||
+ | |||
+ | == Action Items == | ||
+ | * Tim to look at chambers in EEL to determine how big a gap is needed between the DS detectors | ||
+ | * Mark to arrange bring scintillator paddles to EEL | ||
+ | * Mark to arrange getting tables in the EEL | ||
+ | * Beni to get with Scot to hook up gas when ready | ||
+ | * Stephanie to model paddles and x-ray ports in the 3D model and drawings |
Revision as of 15:13, 14 July 2021
Meeting Time and Place
Thursday Jun 17, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/June_17,_2021_CPP_Design_Meeting
- OSP/Testing status - Beni
- Rory slides media:mwpc5&6.pdf
- Design/Fab/Procurement status
- Installation/assy dwgs
- Stand
- Steel
- Fcal platform mods
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
- CPP Detector operations in Hall D OSP
Minutes and Action Items
- Rory discussed the importance of making sure the downstream detector has it's x-ray port facing downstream for access. With this in mind the 2 vertical downstream detectors will need to have a gap in between to accommodate the HV cables protruding past the planes. The x-ray port will be 15inches from the center of the detector
- Elton will label the detectors as the testing goes along to ensure we know what detector is installed where
- Discussed OSP -
- Beni put the OSP on the table for reading and signatures. He will need a table to put the chambers on
- Need scintillator paddles in the EEL 126
- Need to hook up gas to the detector being tested first
- There will be a 10" vacuum tube installed DS of the detector
- 2 scintillator paddles will be installed vertically on the DS end of the detector close to the beam maybe 10" from the center
- We discussed the clearance for the SHV connectors and using a right angle connector. Stephanie reminded us that we had made clearance in the base to allow room for the straight connector.
Action Items
- Tim to look at chambers in EEL to determine how big a gap is needed between the DS detectors
- Mark to arrange bring scintillator paddles to EEL
- Mark to arrange getting tables in the EEL
- Beni to get with Scot to hook up gas when ready
- Stephanie to model paddles and x-ray ports in the 3D model and drawings