Difference between revisions of "Run Planning Meeting Notes, September 30 - October 6, 2021"
From GlueXWiki
(→Thursday, September 30) |
(→Thursday, September 30) |
||
Line 5: | Line 5: | ||
#* Machine maintenance ended, and beam came back around XXX. | #* Machine maintenance ended, and beam came back around XXX. | ||
#* Early Riser summary | #* Early Riser summary | ||
− | #* Owl summary | + | #* [https://logbooks.jlab.org/entry/3914937 Owl summary] |
#* [https://logbooks.jlab.org/entry/3914704 Swing summary] | #* [https://logbooks.jlab.org/entry/3914704 Swing summary] | ||
#* [https://logbooks.jlab.org/entry/3914472 Day summary] | #* [https://logbooks.jlab.org/entry/3914472 Day summary] |
Revision as of 23:56, 29 September 2021
<- Back to Run Coordination Meetings:Summer2021
Thursday, September 30
- In last 24 hours:
- Machine maintenance ended, and beam came back around XXX.
- Early Riser summary
- Owl summary
- Swing summary
- Day summary
- During downtime for maintenance:
- BCAL pedestal calibration (Sergey)
- FCAL base replacementCommunication issue resolved(Rebecca/Mark/Malte)
- Issues:
- Strange behavior in FCAL base (Rebecca/Mark/Malte)
- https://logbooks.jlab.org/entry/3914823
- Bleedthrough
- Plan:
- Before taking data: check radiation level and beam quality (HARP scan)
- 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
- 100 nA CDC & FDC turn off (2 shifts)
- 200 nA CDC & FDC turn off (8.4 shifts)
- Remove Be target to take empty target