=Thursday, October 21= | =Thursday, October 21= | ||
# Last 24h: | # Last 24h: | ||
− | #* No beam from 5:20pm Tuesday until | + | #* No beam from 5:20pm Tuesday until 2am Thurs due to LCW/power problem |
#* Work done during the access: | #* Work done during the access: | ||
− | |||
− | |||
#** [https://logbooks.jlab.org/entry/3928644 magnetic field measurements around CCAL] | #** [https://logbooks.jlab.org/entry/3928644 magnetic field measurements around CCAL] | ||
#** [https://logbooks.jlab.org/entry/3928669 15 FCAL bases replaced] and [https://logbooks.jlab.org/entry/3928811 re-terminated one cable] | #** [https://logbooks.jlab.org/entry/3928669 15 FCAL bases replaced] and [https://logbooks.jlab.org/entry/3928811 re-terminated one cable] | ||
#** [https://logbooks.jlab.org/entry/3928624 faulty FDC chiller replaced] | #** [https://logbooks.jlab.org/entry/3928624 faulty FDC chiller replaced] | ||
#** [https://logbooks.jlab.org/entry/3928742 rebalanced the server power load on rack 13] | #** [https://logbooks.jlab.org/entry/3928742 rebalanced the server power load on rack 13] | ||
+ | #** ? position survey CCAL ? | ||
+ | #** ? correct shielding at the left (downstream) PS arm ? | ||
# Remaining issues: | # Remaining issues: | ||
#* [https://logbooks.jlab.org/entry/3929404 Tagger hodoscope time shifts] | #* [https://logbooks.jlab.org/entry/3929404 Tagger hodoscope time shifts] |
Revision as of 07:29, 21 October 2021
Thursday, October 21
- Last 24h:
- No beam from 5:20pm Tuesday until 2am Thurs due to LCW/power problem
- Work done during the access:
- magnetic field measurements around CCAL
- 15 FCAL bases replaced and re-terminated one cable
- faulty FDC chiller replaced
- rebalanced the server power load on rack 13
- ? position survey CCAL ?
- ? correct shielding at the left (downstream) PS arm ?
- Remaining issues:
- Tagger hodoscope time shifts
- communication with accel. w.r.t. tagger magnet - Paul Vasilauskis (Ops group leader): "I am putting out to my staff to contact the hall if they do need to touch the magnet and am looking into adding wording to the magnet screens"
- BCAL noise at 10 o'clock
- Bleedthrough
- Plan:
- When the beam is back continue production at 200nA after the usual checks (radiation levels & harp scans)
- Continue running with the solenoid on & target full until Friday or later
- Pass change possible Friday or Saturday
- Expect some downtime Monday daytime for VIP tour