Difference between revisions of "JEF meeting, September 30, 2022"
From GlueXWiki
(→Agenda) |
|||
Line 7: | Line 7: | ||
* Simulations/Analysis | * Simulations/Analysis | ||
* Preparation of parts for FCAL2 modules -- Sasha | * Preparation of parts for FCAL2 modules -- Sasha | ||
+ | ** Received 100 PMTs (the last batch) [https://halldweb.jlab.org/wiki-private/index.php/PMT_for_FCAL_insert] | ||
+ | *** All PMTs have been checked (measured diameter) | ||
+ | *** 39 PMTs were exchanged with the NPS (they are slightly tight) | ||
**[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 707 (15 since last week) ] | **[https://halldweb.jlab.org/detectors/fcal2/module_fabrication/wrapped/wrapped_crytur.pdf Wrapped CRYTUR crystals: 707 (15 since last week) ] | ||
*** - Available for wrapping: 722 - 707 = 15 | *** - Available for wrapping: 722 - 707 = 15 |
Revision as of 10:43, 30 September 2022
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Zoom meeting ID: 161 050 9142 Passcode: 004965
Agenda
- Simulations/Analysis
- Preparation of parts for FCAL2 modules -- Sasha
- Received 100 PMTs (the last batch) [1]
- All PMTs have been checked (measured diameter)
- 39 PMTs were exchanged with the NPS (they are slightly tight)
- Wrapped CRYTUR crystals: 707 (15 since last week)
- - Available for wrapping: 722 - 707 = 15
- - DSG group continues wrapping
- Received 100 PMTs (the last batch) [1]
- Module fabrication -- Sasha
- Updates from the FCAL installation meetings with Tim's group -- Sasha
- Light Monitoring System -- Arshak