Difference between revisions of "Run Planning Meeting Notes, October 6 - October 12, 2022"
From GlueXWiki
(→Monday, October 10) |
(→Issues) |
||
Line 23: | Line 23: | ||
=== Issues === | === Issues === | ||
* [https://logbooks.jlab.org/entry/4053026 TOF crate/fADC] (Sasha) | * [https://logbooks.jlab.org/entry/4053026 TOF crate/fADC] (Sasha) | ||
+ | * CDC HV issue with a board newly installed possibly a HV main frame issue, rapid access requested to place the board elsewhere in the frame (Beni) | ||
* No beam for a long time (~8h): Hall A ion chamber calibration, RF issue (CPS breaker tripped, P5 HorizSep Trip, VertSep Cav2 Trip ) | * No beam for a long time (~8h): Hall A ion chamber calibration, RF issue (CPS breaker tripped, P5 HorizSep Trip, VertSep Cav2 Trip ) | ||
* [https://logbooks.jlab.org/entry/4053692 Hole in FCAL for Compton events ] | * [https://logbooks.jlab.org/entry/4053692 Hole in FCAL for Compton events ] |
Revision as of 08:05, 10 October 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Monday, October 10
Past 24 hours
- Starting run 110991, TOF debugged, so far 1B trigger collected
- HARP scan results
- Runs from 110987 to 119990 with TOF North issues
- Rapid access to debug TOF North from 1000 to 1350 on Sunday
- Shift Summary
Issues
- TOF crate/fADC (Sasha)
- CDC HV issue with a board newly installed possibly a HV main frame issue, rapid access requested to place the board elsewhere in the frame (Beni)
- No beam for a long time (~8h): Hall A ion chamber calibration, RF issue (CPS breaker tripped, P5 HorizSep Trip, VertSep Cav2 Trip )
- Hole in FCAL for Compton events
- FDC HV issue (solved) (Lubomir)
- Excursion in y (Hovanes/Brian)
Plan
- Take data with Full Target until ??????
Sunday, October 9
Past 24 hours
- Data collection resumed at 4:19 am with TOF issue
- Beam transmission after long beam down time
- HARP scan
- Beam back at 3:30 am
- Target FULL & Ready at 6:45 pm
- LCW 2 reached at 5 pm on Saturday
- ig is replacing Joerg as RC from Saturday morning until Monday morning
- Shift summary
Issues
Plan
- Rapid access to replace TOF ADC
Thursday, October 6
Past 24 hours
Issues
- MCC still trying to fix magnets
Plan
- Production data on helium target