Difference between revisions of "Run Planning Meeting Notes, October 13 - October 19, 2022"
From GlueXWiki
(→Friday, October 14) |
m |
||
Line 8: | Line 8: | ||
Back to [[Run Coordination Meetings:Fall2022]] | Back to [[Run Coordination Meetings:Fall2022]] | ||
+ | |||
+ | =Saturday, October 15= | ||
+ | === Past 24 hours === | ||
+ | *No beam during most of day shift (Wien angle change + Hall A pass change) | ||
+ | *[https://logbooks.jlab.org/entry/4058479 5 FCAL Bases replaced (Mark)] | ||
+ | *[https://logbooks.jlab.org/entry/4058571 Calorimeter Prototype installed in PS test setup] | ||
+ | *[https://logbooks.jlab.org/entry/4058868 Harp scan results] | ||
+ | *4 hours of data (2 runs) collected at 250nA for Compton systematic studies | ||
+ | *2.1B total triggers collected on He target since 5PM yesterday (as of 8:30AM, Saturday morning). | ||
+ | |||
+ | * Shift Summary | ||
+ | ** [https://logbooks.jlab.org/entry/4059426 Early Riser Saturday] | ||
+ | ** [ Owl Friday/Saturday] | ||
+ | ** [https://logbooks.jlab.org/entry/4058851 Swing Friday] | ||
+ | ** [https://logbooks.jlab.org/entry/4058420 Day Friday] | ||
+ | ** [https://logbooks.jlab.org/entry/4058236 Early Riser Friday] | ||
+ | |||
+ | === Issues === | ||
+ | *Problems reported establishing connection to VNC session by remote worker. Seems to be fixed. | ||
+ | |||
+ | === Plan === | ||
+ | *Continue taking production data at 200nA over the weekend. | ||
+ | |||
=Friday, October 14= | =Friday, October 14= |
Revision as of 10:16, 15 October 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Saturday, October 15
Past 24 hours
- No beam during most of day shift (Wien angle change + Hall A pass change)
- 5 FCAL Bases replaced (Mark)
- Calorimeter Prototype installed in PS test setup
- Harp scan results
- 4 hours of data (2 runs) collected at 250nA for Compton systematic studies
- 2.1B total triggers collected on He target since 5PM yesterday (as of 8:30AM, Saturday morning).
- Shift Summary
- Early Riser Saturday
- [ Owl Friday/Saturday]
- Swing Friday
- Day Friday
- Early Riser Friday
Issues
- Problems reported establishing connection to VNC session by remote worker. Seems to be fixed.
Plan
- Continue taking production data at 200nA over the weekend.
Friday, October 14
Past 24 hours
- ~7:40 am started filling target
- Relatively smooth running on full target
- Shift Summary
- [ Early Riser Wednesday]
- [ Day Wednesday]
- [ Swing Wednesday]
- [ Owl Wednesday/Thursday]
- [ Early Riser Thursday]
- ABUs: ? + 6.4 + 6.7 = hrs
- Data Summary: we collected 2.1B on empty before switching to full target; since then collected ~2.8B on full
Issues
Plan
- Take data with Filled Target until ~???B triggers
- Friday day shift: Wien angle change and pass change for Hall A; (concurrently Hall D Safety training at 9:30 am (M. Dalton)?????????)
- Opportunistic: EIC calorimeter prototype installation at PS calorimeter; need one hour (maybe Thursday?); contact Sasha
- Kondo repositions his detector
- FCAL base change
Thursday, October 13
Past 24 hours
- Relatively smooth running on empty target
- ~7:40 am started filling target
- Shift Summary
- [ Early Riser Wednesday]
- [ Day Wednesday]
- [ Swing Wednesday]
- Owl Wednesday/Thursday
- Early Riser Thursday
- ABUs: 5.4 + 5.2 + 6.8 = 17.4 hrs
- Data Summary: >0.4B triggers on empty target since 16:00 Wednesday -> >1.8B on empty total
Issues
Plan
- Take data with Filled Target until ~???B triggers
- Friday day shift: Wien angle change and pass change for Hall A; (concurrently Hall D Safety training at 9:30 am (M. Dalton)?????????)
- Opportunistic: EIC calorimeter prototype installation at PS calorimeter; need one hour (maybe Thursday?); contact Sasha