Difference between revisions of "Run Planning Meeting Notes, October 26 - November 2, 2022"
From GlueXWiki
(→Past 24 hours) |
|||
Line 8: | Line 8: | ||
Back to [[Run Coordination Meetings:Fall2022]] | Back to [[Run Coordination Meetings:Fall2022]] | ||
+ | |||
+ | =Monday, October 31= | ||
+ | Happy Halloween! | ||
+ | |||
+ | === Past 72 hours === | ||
+ | * Friday afternoon TOF HV module failed, replaced (Beni and Sasha) | ||
+ | * Beam returned early Sunday morning | ||
+ | |||
+ | === Shift Summary === | ||
+ | |||
+ | === Issues/Reports === | ||
+ | |||
+ | === Plan === | ||
+ | * Production running on full target | ||
+ | * Maintenance day on Thursday this week (11/3) | ||
=Friday, October 28= | =Friday, October 28= |
Revision as of 10:34, 29 October 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Monday, October 31
Happy Halloween!
Past 72 hours
- Friday afternoon TOF HV module failed, replaced (Beni and Sasha)
- Beam returned early Sunday morning
Shift Summary
Issues/Reports
Plan
- Production running on full target
- Maintenance day on Thursday this week (11/3)
Friday, October 28
Past 24 hours
- Returned from RF recovery around 6 pm, postponed CompCal calibration run to Friday
- Harp scans performed when beam restored
- Production running until midnight: "smoking gun" for burnt RF power supply
- FDC chiller interlock
Shift Summary
Issues/Reports
Plan
- Recover from accelerator power supply issue by "early afternoon"
- Check calibration of CompCal modules with adjusted HV, 1 hr at low intensity (Sasha)
- Production data with full target
Thursday, October 27
Past 24 hours
- Smooth running with empty target
- 6 CDC Pressure alarms: new run started each time, last one required DAQ crate reboot (delayed restart)
Shift Summary
Issues/Reports
- Avoid long prestarts (Naomi)
- 32 ns shift in tagger crate (no action required)
- Do we still want beam strip charts in the logbook every 2 hours (as noted on white board)?
- SC Dark Current/Rates (Beni)
Plan
- RF recovery for 4 hours this morning, starting at 8 am: target testing, Kondo GEM work, mechanical checks for FCAL-II work
- Expect to start beam recovery around noon
- Fill target before beam returns for production data
- Harp scan after beam is restored, more than a week since the last one (Alexandre)
- Check calibration of CompCal modules with adjusted HV, 1 hr at low intensity (Sasha)
- Production data with full target