Difference between revisions of "Run Planning Meeting Notes, December 7 - December 14, 2022"
From GlueXWiki
(→Friday Dec. 9th) |
|||
Line 9: | Line 9: | ||
= Friday Dec. 9th = | = Friday Dec. 9th = | ||
=== Last 24h === | === Last 24h === | ||
− | *Took LHe data for ~ | + | *We were running pretty smoothly, no major issues |
+ | *Took LHe data for ~3.4B events from yesterday | ||
+ | *Hall-A during today will run at low current 1-µA, and during weekend they will resume running at 36µA | ||
+ | |||
=== Shift Summaries === | === Shift Summaries === | ||
− | *Day shift 12/08 10:00-16:00 | + | *Day shift 12/08 10:00-16:00 https://logbooks.jlab.org/entry/4098611 |
− | *Swing shift 12/08 16:00-22:00 | + | *Swing shift 12/08 16:00-22:00 https://logbooks.jlab.org/entry/4098735 |
− | *OWL 12/08-12/09 22:00-04:00 | + | *OWL 12/08-12/09 22:00-04:00 https://logbooks.jlab.org/entry/4098860 |
− | *Early Riser 12/09 04:00-10:00 | + | *Early Riser 12/09 04:00-10:00 https://logbooks.jlab.org/entry/4098960 |
=== Issues === | === Issues === | ||
− | * | + | * Some FCAL bases were locked up |
=== Short term run plan === | === Short term run plan === | ||
*Take date on LHe FULL target at 200nA beam | *Take date on LHe FULL target at 200nA beam | ||
+ | *TAC run??? | ||
= Thursday Dec. 8th = | = Thursday Dec. 8th = |
Revision as of 09:00, 9 December 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Contents
Friday Dec. 9th
Last 24h
- We were running pretty smoothly, no major issues
- Took LHe data for ~3.4B events from yesterday
- Hall-A during today will run at low current 1-µA, and during weekend they will resume running at 36µA
Shift Summaries
- Day shift 12/08 10:00-16:00 https://logbooks.jlab.org/entry/4098611
- Swing shift 12/08 16:00-22:00 https://logbooks.jlab.org/entry/4098735
- OWL 12/08-12/09 22:00-04:00 https://logbooks.jlab.org/entry/4098860
- Early Riser 12/09 04:00-10:00 https://logbooks.jlab.org/entry/4098960
Issues
- Some FCAL bases were locked up
Short term run plan
- Take date on LHe FULL target at 200nA beam
- TAC run???
Thursday Dec. 8th
Last 24h
- Wednesday was RF recovery day, Hall was in Controlled Access till ~6:30pm, many things where done during access in Hall.
- Hall (Controlled Access):
- Tim worked on Tagger magnet NMR [1]
- Sasha replaced the BCAL fADC [2]
- DIRC checkout (Justin+1).
- Sasha, Vlad, Lubomir, Sergei and Arshak: work in the PS test area.
- Sasha and Arshak installed the prototype for checking LMS https://logbooks.jlab.org/entry/4098555
- Lubomir installed GEM trackers at PS https://logbooks.jlab.org/entry/4098402
- Sasha, Arshak and Malte did some preliminary noise level tests at FCAL
- Mark Stevens: walkthrough for OPS.
- Tim and Eugene checked the man-lift
- Tim and Sasha checked by how much FCal can be pushed back (for some tentative PrimEx systematic measurements).
- Hall (Controlled Access):
- After beam comes back:
- Harp Scans were performed https://logbooks.jlab.org/entry/4098296
- Took LHe data for ~1.7B events from yesterday
Shift Summaries
- Day shift 12/07 10:00-16:00 https://logbooks.jlab.org/entry/4097947
- Swing shift 12/07 16:00-22:00 https://logbooks.jlab.org/entry/4098188
- OWL 12/07-12/08 22:00-04:00 https://logbooks.jlab.org/entry/4098385
- Early Riser 12/08 04:00-10:00 https://logbooks.jlab.org/entry/4098497
Issues
- Tagger magnet
- BCAL Occupancy Hot channel + some channels (might be baseline calibration) https://logbooks.jlab.org/entry/4098568
- DAQ issues
- FDC channel tripping https://logbooks.jlab.org/entry/4098305
- FCal base lock-ups
Short term run plan
- TAC run? (may be on weekend)
- Take date on LHe FULL target at 200nA beam