(Created page with "== Meeting Time and Place == Tuesday, June 04, 2024, 1:00pm Hall D Counting House * Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim W...") |
|||
Line 14: | Line 14: | ||
*** possible moving plan https://www.aerogo.com/products/air-caster-rigging-system/ | *** possible moving plan https://www.aerogo.com/products/air-caster-rigging-system/ | ||
*** Concerms with dust/contamination - Tim to work with ES&H | *** Concerms with dust/contamination - Tim to work with ES&H | ||
− | * Baseline KLF schedule [[media:KLONG | + | * Baseline KLF schedule |
+ | ** [[media:KLONG_2026instl_No_MRI.pdf | KLONG Installation Schedule 2026 with no MRI Magnet]] | ||
+ | ** [[media:KLONG_2025instl_MRI_v2.pdf | KLONG Installation Schedule 2025 with MRI Magnet]] | ||
* Power supply status - On order, due March 2025 | * Power supply status - On order, due March 2025 | ||
* Magnet update (Josh/Stephanie) | * Magnet update (Josh/Stephanie) |
Latest revision as of 08:50, 4 June 2024
Meeting Time and Place
Tuesday, June 04, 2024, 1:00pm Hall D Counting House
- Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Pavel Degtiarenko, Tim Whitlatch, Eugene Chudakov, Josh Ballard
Agenda
- Review minutes from last meeting https://halldweb.jlab.org/wiki/index.php/May_07,_2024_KLONG_CPS_Design_Meeting
- Review new basic 3D model
- Core Section update
- New radiation levels? Pavel
- Layout of magnet and components (Stephanie/Keith)
- Vendor coming next week to demo system
- possible moving plan https://www.aerogo.com/products/air-caster-rigging-system/
- Concerms with dust/contamination - Tim to work with ES&H
- Baseline KLF schedule
- Power supply status - On order, due March 2025
- Magnet update (Josh/Stephanie)
- Radiation levels at coils 2.E+4 Gy for a 10000 hour run
- Plan on using copper dump skid to cool magnet - is it adequate LCW?
- Copper cooling update -
- Status of brazing sample test media:CPS Absorber cooling test sample.pdf
- Lead brick painting is awarded and due back in September
- DeGauss test summer 2024
- June - items due from ERR
- Thermal cycling of tungsten and copper write up - in work - ready in 2 weeks (Tim)