Line 24: | Line 24: | ||
# Review of Action Items | # Review of Action Items | ||
# Updated schedule (Will) | # Updated schedule (Will) | ||
+ | # Discussion of readout options | ||
+ | #* Time for internal review (end of June / beginning of July)? | ||
+ | #* Number of photons per GeV (Sasha and Elton) | ||
+ | #* Budget comparison (Elton) | ||
+ | # Location of FM pmts relative to B-field | ||
# Prototyping | # Prototyping | ||
# Simulations | # Simulations | ||
− | # MOU with USM | + | # Discussions on MOU with USM |
Revision as of 08:59, 20 May 2009
Teleconference Time: 11:00 a.m. EST
- EVO session
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 00406402# (remember the "#")
Items for followup from previous meeting
- Bcal section
- Zisis will get a quote from Ross machining to find out how much it would cost to polish a segment (both ends)
- JLab to determine how many fibers could be spared now to use in this project.
-
Elton: Feedback to Will on estimate of photons in Bcal - Will, update references on "alternative readout page" with those found by Zisis
- Zisis, Elton: Suggestion to USM on testing prototype
- USM: sketch of test setup to facilitate feedback
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Updated schedule (Will)
- Discussion of readout options
- Time for internal review (end of June / beginning of July)?
- Number of photons per GeV (Sasha and Elton)
- Budget comparison (Elton)
- Location of FM pmts relative to B-field
- Prototyping
- Simulations
- Discussions on MOU with USM