Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 1-Oct-2009 10am CC FL207
Agenda
- Temperature measurement circuits - Elliott
- P&I, narrative status - Mark S, George, Mark W
- U-tube situation - Tom
- Coil 2 cost/schedule review, etc. - George
- Status of platform structural review - George
- Status of ordering platform and components - George, Tom
- Status of magnet support components - George
- Coil 1 repair and testing status - George
- IUCF statement of work, visit, shipping rails from IUCF to JLab - George, Tom
- Controls drawings modifications - Mark S
- PLC programming and testing - Mark W
- Piping design - Tom
- Review "Top To-Do" items - Elliott
- Review of recent progress, identify action items - All