Difference between revisions of "Minutes-4-8-2010"
From GlueXWiki
Line 10: | Line 10: | ||
#* finalizing PCB design | #* finalizing PCB design | ||
#* cable procurement | #* cable procurement | ||
− | # Cathode redesign (Bill, Roger) | + | # Cathode redesign [http://www.jlab.org/Hall-D/detector/fdc/drawings/cathode_foil_redesign.pdf] (Bill, Roger) |
# Redesigned frame prototype | # Redesigned frame prototype | ||
#* plans for tests | #* plans for tests |
Revision as of 09:57, 8 April 2010
April 8, 2010 FDC meeting
Tentative Agenda
- Off-site production space
- status
- requirements, floor plan
- Electronics (Fernando)
- finalizing PCB design
- cable procurement
- Cathode redesign [1] (Bill, Roger)
- Redesigned frame prototype
- plans for tests
- Full scale prototype (Beni)
- two-layer HV tests
- third layer status
- preparation for cosmics tests
- Other