Difference between revisions of "Coil Test Weekly Meeting 6-May-2010"
From GlueXWiki
m |
m |
||
Line 11: | Line 11: | ||
* Safety review - OSP and COO - Elliott, Josh, Tim | * Safety review - OSP and COO - Elliott, Josh, Tim | ||
** subject matter experts | ** subject matter experts | ||
− | ** what drawings are needed - final P&I, etc. | + | ** what drawings are needed - final P&I, wiring diagrams, etc. |
** what documents are needed - writing assignments | ** what documents are needed - writing assignments | ||
− | ** next meeting with Bob May | + | ** next meeting with Bob May et al. |
− | * | + | * Review of instrumentation controllers and final controls equipment order - Elliott |
* Failure analysis and machine protection - Scot, Mark S, Josh, Elliott | * Failure analysis and machine protection - Scot, Mark S, Josh, Elliott | ||
* Wiring and testing controls racks - Scot, Mark S | * Wiring and testing controls racks - Scot, Mark S | ||
− | ** | + | ** "cheater boxes" |
− | + | ** When to moving PLC from ARC 101 to F117 for testing | |
* Status of PLC programming - Mark W | * Status of PLC programming - Mark W | ||
** Lakeshore calibrations | ** Lakeshore calibrations | ||
− | * HMI and EWEB programming | + | * HMI and EWEB programming - Yi, Elliott |
** Status of developing display pages and archiving | ** Status of developing display pages and archiving | ||
* EPICS connection to PLC - Elliott, Wesley | * EPICS connection to PLC - Elliott, Wesley |
Revision as of 09:58, 4 May 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 6-May-2010 9:30am ARC 428
Agenda
- Safety review - OSP and COO - Elliott, Josh, Tim
- subject matter experts
- what drawings are needed - final P&I, wiring diagrams, etc.
- what documents are needed - writing assignments
- next meeting with Bob May et al.
- Review of instrumentation controllers and final controls equipment order - Elliott
- Failure analysis and machine protection - Scot, Mark S, Josh, Elliott
- Wiring and testing controls racks - Scot, Mark S
- "cheater boxes"
- When to moving PLC from ARC 101 to F117 for testing
- Status of PLC programming - Mark W
- Lakeshore calibrations
- HMI and EWEB programming - Yi, Elliott
- Status of developing display pages and archiving
- EPICS connection to PLC - Elliott, Wesley
- Installation progress - George
- Coil 1 status - George
- Coil 2 status - George
- Coil 3 repairs at IUCF - George