Difference between revisions of "Coil Test Weekly Meeting 6-May-2010"
From GlueXWiki
m |
m |
||
Line 15: | Line 15: | ||
** next meeting with Bob May et al. | ** next meeting with Bob May et al. | ||
* Review of instrumentation controllers and final controls equipment order - Elliott | * Review of instrumentation controllers and final controls equipment order - Elliott | ||
− | * Failure analysis | + | * Failure analysis, machine protection, safety interlocks - Scot, Mark S, Josh, Elliott |
* Wiring and testing controls racks - Scot, Mark S | * Wiring and testing controls racks - Scot, Mark S | ||
** "cheater boxes" | ** "cheater boxes" |
Revision as of 09:59, 4 May 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 6-May-2010 9:30am ARC 428
Agenda
- Safety review - OSP and COO - Elliott, Josh, Tim
- subject matter experts
- what drawings are needed - final P&I, wiring diagrams, etc.
- what documents are needed - writing assignments
- next meeting with Bob May et al.
- Review of instrumentation controllers and final controls equipment order - Elliott
- Failure analysis, machine protection, safety interlocks - Scot, Mark S, Josh, Elliott
- Wiring and testing controls racks - Scot, Mark S
- "cheater boxes"
- When to moving PLC from ARC 101 to F117 for testing
- Status of PLC programming - Mark W
- Lakeshore calibrations
- HMI and EWEB programming - Yi, Elliott
- Status of developing display pages and archiving
- EPICS connection to PLC - Elliott, Wesley
- Installation progress - George
- Coil 1 status - George
- Coil 2 status - George
- Coil 3 repairs at IUCF - George