* OSP status - Elliott | * OSP status - Elliott | ||
* Hall probe - Mark S | * Hall probe - Mark S | ||
− | * Installation status - all | + | * Installation adn commissioning status - all |
− | ** what | + | ** pressure testing |
+ | ** pumping/purging | ||
+ | ** connection to cryo system | ||
+ | ** what else? | ||
* Magnet power supply and interlock commissioning - Mark S | * Magnet power supply and interlock commissioning - Mark S | ||
** shunt and ground fault detection | ** shunt and ground fault detection |
Revision as of 09:48, 20 October 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 21-Oct-2010 9:30 am ARC 428
Agenda
- Responsibilities during test - Jonathan
- OSP status - Elliott
- Hall probe - Mark S
- Installation adn commissioning status - all
- pressure testing
- pumping/purging
- connection to cryo system
- what else?
- Magnet power supply and interlock commissioning - Mark S
- shunt and ground fault detection
- Controls racks - Scot
- strain gauge and UPS interlocks
- commissioning
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- what's left?
- EPICS - Hovanes
- communication with PLC
- connection to guard shack and notification conditions
- pager status and strategy
- HMI and EWEB programming - Yi, Hovanes
- current status
- Coil repair status - George
- Solenoid reviews 25-26 Oct and 7-Dec
- Purchase of another PLC and Ethernet module - Elliott
- Hall D Technical web page
- Preparations for testing next coil - George, Scot, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring
- connectors on next coil
- what else?