Difference between revisions of "Minutes-7-14-2011"

From GlueXWiki
Jump to: navigation, search
Line 17: Line 17:
 
# Other: [http://www.jlab.org/Hall-D/detector/fdc/tracking/FDC_NamingConvention.pdf naming convention]
 
# Other: [http://www.jlab.org/Hall-D/detector/fdc/tracking/FDC_NamingConvention.pdf naming convention]
  
<!--
 
  
 
= Minutes =
 
= Minutes =
  
Participants: Eugene, Bill, Dave, Chris, Beni, Simon, Caleb, and Lubomir.
+
Participants: Bill, Dave, Chris, Elton, Beni, Simon, Glenn, Caleb, and Lubomir.
  
 
== Production ==
 
== Production ==
  
- Dave: see  the construction tracking link above. For cell#3: gluing the rigid-flexes on the cathodes, some delay here was due problems with the connectors on three of the rigid-flexes and also we run out of tinned flexes and Casey had to tin the un-tinned. We continued with the wire frame#3, we postponed the production for a week since we were not sure about the problem with the frame deformation. The wires were taped and position measurements were done with the new code. Caleb reported that the number of field wires that can't be find increased from the last week. Techs are working on the cell#4 cathodes.
+
- Dave (see  the construction tracking): Cell#3 is almost ready, just second phase elements has to be put on the wire frame. The cathodes on cell#4 are ready except the flaps on the type-2 cathode. Now the techs are working on the cathodes for cell#5. We are using now the two tensioning tools. We decided to postpone the wire frame production till we make a decision how to solve the HV problem, discussed later.  
  
- Lubomir on second cell tests: it was conditioned over the holidays
+
- Wire deadening: waiting for the chemicals needed. We will use the square lexan plate for tooling, but Bill will order another plate to be used for this procedure. Bill talking to Brian learned that the chemicals have to be neutralized at the end of the proocedure and that was not always done before when experimenting on a testing wire frame. We will try the deadening first on several testing frames before using a production one. Dave with Al's help is finishing the micro-controller and also working on a way to bypass the 1M resistors on each wire channel.  
by Anatoly (it took a week in total) and now it holds 2200V, but still
+
tripping every 2-3 hours. The trips might be due to the lexan sheet on the top.
+
Bill proposed to make it conductive for the future tests.
+
The current is very low, 140nA for the whole
+
chamber, especially compared to the first chamber that in similar conditions
+
had ~500nA on one sector and several uA on the rest.
+
 
+
- To find the origin of the current and trips, we checked separately
+
on another laminated wire frame: (1) the current through the HV boards and
+
found to be very small (so the Rohacell is not contributing to the current!)
+
(2) the current through the HV capacitors on the signal side:
+
this current turned out to be significant, between 10 nA and few hundred nA
+
at 2200V.  For 96 capacitors one would expect > 1 uA.
+
We will continue investigating the capacitors.
+
  
 
== Engineering ==
 
== Engineering ==
  
- Survey of the first package showed out of plane deviations up to 5.5mm in
+
- Bill ordered the strong-back for the packages. One option would be to attach it to the package after it is assembled, and the other is just to assmble the package on the top of the strong-back in which case we need several of them. We want to have flatness on the chambers better than 200 microns, but Bill says with the material we have it is hardly possible.  
horizontal position and that effect goes with the gravity, and ~1mm in
+
vertical position. This explains the top/bottom asymmetry results.
+
  
 
- Bill explained the current design of the connections between the packages.
 
- Bill explained the current design of the connections between the packages.

Revision as of 17:20, 14 July 2011

July 14, 2011 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Status
    • Wire deadening
  2. Engineering (Bill)
    • Flatness problem: package strongback, gusset rings
    • Stringing table modifications
  3. Electronics (Chris)
    • HV tests
    • Other
  4. Chamber testing at EEL126
    • First cell tests with fADC: cathode resolution(Lubomir)
    • Tests with external tracking (Beni)
  5. Other: naming convention


Minutes

Participants: Bill, Dave, Chris, Elton, Beni, Simon, Glenn, Caleb, and Lubomir.

Production

- Dave (see the construction tracking): Cell#3 is almost ready, just second phase elements has to be put on the wire frame. The cathodes on cell#4 are ready except the flaps on the type-2 cathode. Now the techs are working on the cathodes for cell#5. We are using now the two tensioning tools. We decided to postpone the wire frame production till we make a decision how to solve the HV problem, discussed later.

- Wire deadening: waiting for the chemicals needed. We will use the square lexan plate for tooling, but Bill will order another plate to be used for this procedure. Bill talking to Brian learned that the chemicals have to be neutralized at the end of the proocedure and that was not always done before when experimenting on a testing wire frame. We will try the deadening first on several testing frames before using a production one. Dave with Al's help is finishing the micro-controller and also working on a way to bypass the 1M resistors on each wire channel.

Engineering

- Bill ordered the strong-back for the packages. One option would be to attach it to the package after it is assembled, and the other is just to assmble the package on the top of the strong-back in which case we need several of them. We want to have flatness on the chambers better than 200 microns, but Bill says with the material we have it is hardly possible.

- Bill explained the current design of the connections between the packages. We exchanged different ideas how to use this construction to correct for the out-of-plane deviations of the packages.

- One of the gusset rings is ready and we can start re-assembling the second cell. A survey of the strong-back for the wire frame showed sagging of ~2mm. Bill says it is easy to correct it and it will do it after we are done with the third wire frame. We discussed also what do we need to start the wire deadening.

Electronics

- Chris: 80 FDC type-1 cables were tested, found one bad. Another 130 FDC cables came, not tested yet. - Eugene: all the ASICS will be ready by the end of the month, but making the pre-amp cards will take many months.

Chamber testing

- As before, we can use one out of four HV sectors. After having understood the effects of the frame deformation, we are now studying the chamber resolution. So far it's not as good as on prototype, especially on the top strips. However, by swapping the cards at the detector it turned out that the effect goes with the card. So, the problem could be in the cards, cables, fADC, or the analysis code.

Other

- Eugene asked Dave how we are the production schedule. Dave: we are late by about a month but expect the be on track for the first package.

-->