Difference between revisions of "Minutes-7-14-2011"

From GlueXWiki
Jump to: navigation, search
Line 34: Line 34:
 
- While the stringing table is not used for now, Bill will modify the strong-back to correct for the flatness deviations. Additional holes needed for the frame ejection tool will be drilled, as well.   
 
- While the stringing table is not used for now, Bill will modify the strong-back to correct for the flatness deviations. Additional holes needed for the frame ejection tool will be drilled, as well.   
  
<!--
 
  
 
== Electronics ==
 
== Electronics ==
  
- Chris: 80 FDC type-1 cables were tested, found one bad. Another 130 FDC cables came, not tested yet.
+
- Lubomir and Anatoly made some tests to study the currents through the HV capacitors. At Blue Crab, one wire frame without wires was put in a gas volume and HV was applied on the signal boards between the wire pads (connected with Cu tape) and the ground. The conditining of this "wireless" chamber turned out to be very similar to the behaviour of the second cell and maybe even worse. After almost a week we could reach only ~1.5kV while limiting the current below 1uA for the whole chamber. This indicates that the HV problems we had with cell#2 could be related to the capacitors on the signal boards.
- Eugene: all the ASICS will be ready by the end of the month, but making the pre-amp cards will take many months.
+
 
 +
- Fernando and Chris did simillar tests with one signal board in 117. Initially the current was huge, few hundred uA at 1kV. Then Fernando suggested to cover the capcitors with humiseal and that helped. Initially the current was also high but on the next day it went down to ~13uA at 2kV for the whole board.
 +
 
 +
- Beni: these currents are much bigger than on the prototype and 
 +
 
 +
<!--
  
 
== Chamber testing ==
 
== Chamber testing ==

Revision as of 18:11, 14 July 2011

July 14, 2011 FDC meeting

Agenda

  1. Production Construction Tracking (Dave)
    • Status
    • Wire deadening
  2. Engineering (Bill)
    • Flatness problem: package strongback, gusset rings
    • Stringing table modifications
  3. Electronics (Chris)
    • HV tests
    • Other
  4. Chamber testing at EEL126
    • First cell tests with fADC: cathode resolution(Lubomir)
    • Tests with external tracking (Beni)
  5. Other: naming convention


Minutes

Participants: Bill, Dave, Chris, Elton, Beni, Simon, Glenn, Caleb, and Lubomir.

Production

- Dave (see the construction tracking): Cell#3 is almost ready, just second phase elements has to be put on the wire frame. The cathodes on cell#4 are ready except the flaps on the type-2 cathode. Now the techs are working on the cathodes for cell#5 using the two tensioning tools. We decided to postpone the wire frame production till we make a decision how to solve the HV problem, discussed later.

- Wire deadening: waiting for the chemicals needed. We will use the square lexan plate for tooling, but Bill will order another plate to be used for this procedure. Bill talking to Brian learned that the chemicals have to be neutralized at the end of the proocedure and that was not always done before when experimenting on a testing wire frame. We will try the deadening first on several testing frames before using a production one. Dave with Al's help is finishing the micro-controller and also working on a way to bypass the 1M resistors on each wire channel.

Engineering

- Bill ordered the strong-back for the packages. One option would be to attach it to the package after it is assembled, and the other is just to assemble the package on the top of the strong-back in which case we need several of them. We want to have flatness on the chambers better than 200 microns, but Bill says with the material budget we have it is hardly possible. Measurements on the gusset ring only show deviation from flat up to 150 microns. The biggest deviation correlates with some scratches made in the production and Bill wants to re-enforce that place with epoxied fiber.

- While the stringing table is not used for now, Bill will modify the strong-back to correct for the flatness deviations. Additional holes needed for the frame ejection tool will be drilled, as well.


Electronics

- Lubomir and Anatoly made some tests to study the currents through the HV capacitors. At Blue Crab, one wire frame without wires was put in a gas volume and HV was applied on the signal boards between the wire pads (connected with Cu tape) and the ground. The conditining of this "wireless" chamber turned out to be very similar to the behaviour of the second cell and maybe even worse. After almost a week we could reach only ~1.5kV while limiting the current below 1uA for the whole chamber. This indicates that the HV problems we had with cell#2 could be related to the capacitors on the signal boards.

- Fernando and Chris did simillar tests with one signal board in 117. Initially the current was huge, few hundred uA at 1kV. Then Fernando suggested to cover the capcitors with humiseal and that helped. Initially the current was also high but on the next day it went down to ~13uA at 2kV for the whole board.

- Beni: these currents are much bigger than on the prototype and