# Check on status of shipping of bcal slices (Elton) | # Check on status of shipping of bcal slices (Elton) | ||
# Elton to send monitoring specification to Jim. | # Elton to send monitoring specification to Jim. | ||
+ | # Confirm the number of wires in the Fisher bias connector to the board. Jim will send Fernando the precise connector number. | ||
== Tentative Agenda == | == Tentative Agenda == |
Revision as of 08:45, 11 November 2011
Action Items from previous meetings
- Jack to update board with bias compensation circuitry (Jack)
- Check on status of shipping of bcal slices (Elton)
- Elton to send monitoring specification to Jim.
- Confirm the number of wires in the Fisher bias connector to the board. Jim will send Fernando the precise connector number.
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- Light source / optics
- Electronic boards
- Cabling
- Cooling plate
- Programming
- Other?
- SiPM testing (Ivan)
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Preamp-summing (Fernando)
Minutes
Attending: