Difference between revisions of "Oct 9, 2012 Calorimetry"
From GlueXWiki
(→Minutes) |
(→Minutes) |
||
Line 66: | Line 66: | ||
## Fcal (Matt) | ## Fcal (Matt) | ||
##* Writing will start early next month. Hope to update the Fcal section from previous reports and reviews. | ##* Writing will start early next month. Hope to update the Fcal section from previous reports and reviews. | ||
− | # | + | # Simulations |
− | # | + | #* David: To generate the 2B events for the data challenge, there is a problem with the latest update to the Bcal simulation, which causes inefficiencies. It was decided to go back to an earlier version to avoid confusion over new software developments. |
+ | #* Matt: Who is going to be responsible for the Bcal software longterm? The plan is for UofR to take over this responsibility and will have some cycles starting in a couple of months. | ||
# Any other business | # Any other business |
Latest revision as of 15:14, 9 October 2012
Teleconference Time: 11:00 a.m. EST
- ESNET (Number is 8542553) and EVO session (GlueX Calorimetry meeting room)
- Phone connection only upon request.
- +1-866-740-1260 : US+Canada
- +1-303-248-0285 : International
- then enter participant code: 3421244# (remember the "#").
- or www.readytalk.com (and code without the #)
Contents
[hide]Participant Direct Lines
- JLab Phone: in CC F326 is 757-269-6460 (usual room)
- JLab Phone in CC L207 is 757-269-7084
- Phone in the Regina Videoconference Suite is 306-585-4204
- Athens Phone: in Christina's office is 011-30-210-727-6947
Items for followup from previous meeting(s)
- Fcal
- Add beam hole for the ABS upstream cover. (Matt)
-
Feedback to IU on drawings that have been shipped (Tim and Chuck)Section drawings sent
- SiPMs
-
Update MySQL Database At UTFSM with detailed description of contents of database entries.Work on this offline
-
- Light Guides
-
Send excel sheet with progress information to Elton. (Francisco)
-
- Simulation
- Add up-to-date geometry for plexiglass pane and TOF detector and rerun simulation to check photon reconstruction
Tentative Agenda
- Announcements
- Review of Action Items
- Monitoring
- FCAL
- USM update
- SiPM Update (Javiera)
- BCAL
- TDR update
- Instructions for the TDR (You must be logged into the wiki to access this page).
- Calibration of Calorimeters
- Any other business
Minutes
Attendees:Elton, David, Dan, Yi, Beni (JLab); Alam, Javiera, Francisco, Ricardo (USM); Matt (IU); Zisis, Andrei (UofR).
- Announcements
- Collaboration meeting last week, so take up some loose ends today.
- Review of Action Items
- Monitoring
- FCAL
- Drawings
- Tim has given his approval for drawings at this stage. More work needs to be done on the dark room before additional reviews/feedback is needed.
- Need to add geometry of new TOF and plexiglass panes to check for changes in photon reconstruction. Elton will check with Beni and/or Richard to add the geometry. Matt can do the simulations. Tim/Chuck have the latest dimensions for the plexiglass and the tof.
- Drawings
- USM update
- SiPM Update (Javiera)
- Next shipment to JLab will be 280 units.
- Elton: Need to order 360+10 SiPMs from Hamamatsu
- Description of entries into the data base needs to be defined more clearly. (Elton will work with USM offline to clarify the definitions).
- Francisco: Request for Hamamatsu to send final shipment depends on payments from JLab. Elton will check on the status of payments from finance. [Note added: All invoices were paid by the end of Sep].
- Light guides
- Francisco: They will ship 400 guides next week.
- SiPM Update (Javiera)
- BCAL
- TDR
- Bcal (Zisis)
- Additions to the Fcal TDR have been checked in (history, geometry, LED monitoring, SiPMs, Fibers, beam tests). Next, measurements on cosmics.
- Fcal (Matt)
- Writing will start early next month. Hope to update the Fcal section from previous reports and reviews.
- Bcal (Zisis)
- Simulations
- David: To generate the 2B events for the data challenge, there is a problem with the latest update to the Bcal simulation, which causes inefficiencies. It was decided to go back to an earlier version to avoid confusion over new software developments.
- Matt: Who is going to be responsible for the Bcal software longterm? The plan is for UofR to take over this responsibility and will have some cycles starting in a couple of months.
- Any other business