(Created page with "== Action Items from previous meetings == # Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elto...")
 
(Tentative Agenda)
Line 10: Line 10:
 
# Action Items
 
# Action Items
 
# Schedule for production and testing (all)
 
# Schedule for production and testing (all)
#* Schedule for production (Fernando and Jim)
 
#* Schedule for SiPM assignment and jumper sheets
 
 
# mini-Bcal (Elton)
 
# mini-Bcal (Elton)
 
# SiPM production testing (Yi)
 
# SiPM production testing (Yi)
Line 17: Line 15:
 
# Temperature compensation (Jack)
 
# Temperature compensation (Jack)
 
# Electronic boards (Fernando and Chris)
 
# Electronic boards (Fernando and Chris)
#* U-board puller?
 
 
# Light guide gluing setup (Scot)
 
# Light guide gluing setup (Scot)
  
 
== Minutes ==
 
== Minutes ==
 
''Attending:
 
''Attending:

Revision as of 15:45, 1 November 2012

Action Items from previous meetings

  1. Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando)
  2. Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim)
  3. Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule for production and testing (all)
  4. mini-Bcal (Elton)
  5. SiPM production testing (Yi)
  6. Mechanical assembly (Jim)
  7. Temperature compensation (Jack)
  8. Electronic boards (Fernando and Chris)
  9. Light guide gluing setup (Scot)